# Lessons Report

- Framework: [PRINCE2](https://pmdecoder.com/en/framework/prince2/)
- Reference: PRINCE2 7, Managementprodukte
- Edition: PRINCE2 7
- Concept: [Captured lessons from projects](https://pmdecoder.com/en/concept/captured-lessons-from-projects/)
- Topic area: [Closing](https://pmdecoder.com/en/area/closing/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/lessons-report/

## Definition

In PRINCE2 the Lessons Report is the report through which a project makes its experience usable beyond itself. It summarizes the main entries of the Lessons Log, puts them in context and derives recommendations, for example for the organization’s standards, templates, estimating data or training. Typical occasions are the end of a management stage and project closure, but it can be produced at any time if a lesson should be passed on immediately. The Project Manager prepares it; the Project Board reviews it and decides to whom it is forwarded. Its content covers what went well and what went badly, the causes that can be identified, where useful measurements of effort and quality, and concrete proposals.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | [Lessons learned](https://pmdecoder.com/en/glossary/lessons-learned-iso/) | closely related | Report that evaluates selected lessons and passes them on to the organization. |
| PMI / PMBOK Guide | [Lessons learned](https://pmdecoder.com/en/glossary/lessons-learned/) | closely related | Report that evaluates selected lessons and passes them on to the organization. |
| PM² | [Project-End Report](https://pmdecoder.com/en/glossary/project-end-report/) | partially overlapping | contains lessons learned, but also reports on the performance and outcome of the project |
| Scrum | [Sprint Retrospective](https://pmdecoder.com/en/glossary/sprint-retrospective/) | partially overlapping | continually improves the way the team works instead of documenting lessons for other initiatives |

## Distinction

The Lessons Log collects experience continuously; the Lessons Report is the selected, evaluated version for recipients outside the project. The End Project Report evaluates the project’s overall performance and can refer to the Lessons Report. The PM² Project-End Report combines both purposes in one document. Lessons learned are the insights themselves; the Lessons Report is the vehicle that carries them.

## In practice

After the first stage of a project introducing electronic case files, the project manager notes that the data protection review of each new module took three weeks because it only started after completion. She writes a short Lessons Report recommending that the data protection officer be involved at the design stage. The Project Board forwards it to the project office, which adds the recommendation to the template for project plans.

## Frequently asked questions

### Does a Lessons Report have to wait until the project ends?

No. It is often produced at the end of a stage or the project, but can be written at any time if a lesson is urgent for other undertakings.

### Who receives the Lessons Report?

The Project Board reviews it and decides on distribution, for example to a project office, to the quality management function or to projects running in parallel.

## Related terms

- [Lessons Log](https://pmdecoder.com/en/glossary/lessons-log/)
- [Lessons learned](https://pmdecoder.com/en/glossary/lessons-learned-iso/)
- [Lessons learned](https://pmdecoder.com/en/glossary/lessons-learned/)
- [Project-End Report](https://pmdecoder.com/en/glossary/project-end-report/)
- [End Project Report](https://pmdecoder.com/en/glossary/end-project-report/)
- [Knowledge management](https://pmdecoder.com/en/glossary/knowledge-management/)
- [Learn from experience principle](https://pmdecoder.com/en/glossary/learn-from-experience-principle/)
- [Closing a project](https://pmdecoder.com/en/glossary/closing-a-project/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.