# Lessons learned

- Framework: [ISO 21506](https://pmdecoder.com/en/framework/iso-21506/)
- Reference: ISO 21506:2024, 3.34
- Edition: ISO 21506:2024
- Concept: [Captured lessons from projects](https://pmdecoder.com/en/concept/captured-lessons-from-projects/)
- Topic area: [Closing](https://pmdecoder.com/en/area/closing/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/lessons-learned-iso/

## Definition

Lessons learned are insights that an undertaking draws from its own course, from successes as well as from mistakes. They describe a situation, how the team dealt with it, what came of it and how things should be done in future. According to ISO 21506, they are gathered throughout the undertaking, not only at closure, and they apply to programmes and portfolios just as much as to projects. They only deliver value once they are filed so that they can be found and are actually used in new undertakings.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Lessons learned](https://pmdecoder.com/en/glossary/lessons-learned/) | equivalent | — |
| PRINCE2 | [Lessons Report](https://pmdecoder.com/en/glossary/lessons-report/) | closely related | Report that evaluates selected lessons and passes them on to the organization. |
| PRINCE2 | [Learn from experience principle](https://pmdecoder.com/en/glossary/learn-from-experience-principle/) | partially overlapping | Principle of using lessons at the start, throughout and at the end, not the lessons themselves. |
| PRINCE2 | [Lessons Log](https://pmdecoder.com/en/glossary/lessons-log/) | partially overlapping | Log in which lessons are collected during the project. |
| PRINCE2 | [End Project Report](https://pmdecoder.com/en/glossary/end-project-report/) | partially overlapping | Mainly evaluates project performance; lessons can be summarized in it or attached as a Lessons Report. |
| PM² | [Project-End Report](https://pmdecoder.com/en/glossary/project-end-report/) | partially overlapping | contains lessons learned, but also reports on the performance and outcome of the project |
| Scrum | [Sprint Retrospective](https://pmdecoder.com/en/glossary/sprint-retrospective/) | partially overlapping | continually improves the way the team works instead of documenting lessons for other initiatives |

## Distinction

Project documentation records what happened; lessons learned draw conclusions from it for the future. A retrospective in agile teams is a regular meeting in which such insights are gained. The PMBOK Guide uses the same term.

## In practice

A plant engineering company used to hold a closing workshop after each project, but nobody read the minutes. It therefore introduces a searchable knowledge base and requires entries after every milestone. Each entry states the trigger, the effect and a recommendation and is tagged by industry and plant type. When costing a new power station, the team finds three entries about delayed customs clearance in the same country and plans a six-week schedule buffer.

## Frequently asked questions

### When should lessons learned be collected?

Continuously, for example after milestones, phases or notable events. Anyone who waits until the end of the project has forgotten much, and the team is often already tied up in new tasks.

### Why do lessons learned often have no effect?

Because they are collected but not prepared and filed in a way that others can find. They become effective when new undertakings explicitly consult them during planning and risk analysis.

## Related terms

- [Lessons learned](https://pmdecoder.com/en/glossary/lessons-learned/)
- [Preventive action](https://pmdecoder.com/en/glossary/preventive-action/)
- [Knowledge management](https://pmdecoder.com/en/glossary/knowledge-management/)
- [Project closure](https://pmdecoder.com/en/glossary/project-closure/)
- [Sprint Retrospective](https://pmdecoder.com/en/glossary/sprint-retrospective/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.