# Lean construction

- Framework: [Lean](https://pmdecoder.com/en/framework/lean/)
- Canonical version: https://pmdecoder.com/en/glossary/lean-construction/

## Definition

Lean construction applies principles such as focus on value, flow, pull and continuous improvement to building. Unlike series production, every building is a one-off created at changing locations with changing participants. The focus is therefore on reliable planning, the removal of constraints before execution and collaboration between client, designers and contractors. Widely used methods are the Last Planner System and takt planning with takt control. The field has been developed in research and practice since the 1990s; today there are associations promoting it in many countries.

## Equivalents in other frameworks

No equivalents have been recorded for this term yet.

## Classification

- Narrower terms: [Last Planner System](https://pmdecoder.com/en/glossary/last-planner-system/)

## Distinction

Lean construction is not a framework of its own but the application of Lean to one industry. The Last Planner System is one of its methods. Collaborative contract models such as alliance contracts are often associated with lean construction, but they are contractual arrangements and not part of the method itself. Building information modelling is a digital design method that can support lean construction.

## In practice

A hospital operator tenders the construction of a new hospital with the requirement to work according to lean construction. Designers and contractors define the sections in joint meetings, the shell construction follows a takt of one week per section, and weekly planning meetings of the foremen clear constraints in advance. A project room on site shows the takt, constraints and metrics to everyone involved.

## Frequently asked questions

### Is lean construction worthwhile for smaller building projects too?

Individual elements such as joint weekly planning and early clearing of constraints can be used with little effort even on smaller projects. Full takt planning pays off above all when there are many similar sections.

### Does lean construction require special contracts?

Not necessarily. Traditional contracts allow joint planning but often set incentives that work against each other. Collaborative models are therefore frequently chosen in addition.

## Related terms

- [Last Planner System](https://pmdecoder.com/en/glossary/last-planner-system/)
- [Takt time](https://pmdecoder.com/en/glossary/takt-time/)
- [Pull principle](https://pmdecoder.com/en/glossary/pull-principle/)
- [Muda](https://pmdecoder.com/en/glossary/muda/)
- [Obeya](https://pmdecoder.com/en/glossary/obeya/)

---