# Lead

- Framework: [ISO 21506](https://pmdecoder.com/en/framework/iso-21506/)
- Reference: ISO 21506:2024, 3.33
- Edition: ISO 21506:2024
- Concept: [Brought-forward start relative to the predecessor](https://pmdecoder.com/en/concept/brought-forward-start-relative-to-the-predecessor/)
- Topic area: [Network planning](https://pmdecoder.com/en/area/network-planning/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/lead/

## Definition

A lead allows two linked activities to overlap. With a finish-to-start relationship and a lead of five days, the successor starts five days before its predecessor ends. In the network schedule it is entered as a negative time offset. It reflects the fact that follow-on work can begin with interim results without abandoning the dependency altogether.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Lead](https://pmdecoder.com/en/glossary/lead-pmi/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

Lag is the counterpart and enforces a waiting time between two activities. In general usage, lead time also refers to the time between ordering and availability, such as the delivery time of a machine; in the schedule, such a period is usually shown as a separate activity. A lead is one of the means used in fast tracking.

## In practice

An editorial team is producing an annual report. Layout can begin once two thirds of the texts are ready, because the basic design does not depend on the last chapters. The project manager links writing and layout with a finish-to-start relationship and a ten-day lead. As a result, the report is published two weeks earlier. When one chapter is heavily rewritten, a few hours of layout rework arise, as expected.

## Frequently asked questions

### How is a lead entered in scheduling software?

Usually as a negative offset on the link, for example minus five days, sometimes also as a percentage of the predecessor's duration.

### What is the risk of a lead?

The successor works with unfinished results. If these still change, rework follows.

## Related terms

- [Lag](https://pmdecoder.com/en/glossary/lag/)
- [Logical relationship](https://pmdecoder.com/en/glossary/logical-relationship/)
- [Fast tracking](https://pmdecoder.com/en/glossary/fast-tracking/)

---