# Lead

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Brought-forward start relative to the predecessor](https://pmdecoder.com/en/concept/brought-forward-start-relative-to-the-predecessor/)
- Topic area: [Network planning](https://pmdecoder.com/en/area/network-planning/)
- Canonical version: https://pmdecoder.com/en/glossary/lead-pmi/

## Definition

A lead is a time value on a logical relationship that allows a successor to start earlier than the relationship alone would permit. In a finish-to-start relationship with a lead of five days, the successor starts five days before the predecessor finishes. This makes it possible to represent overlaps when part of the predecessor is enough to begin the follow-on work. Many scheduling tools enter a lead as a negative lag.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | [Lead](https://pmdecoder.com/en/glossary/lead/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

Lead corresponds to the German Vorlaufzeit in ISO 21506. Its counterpart is lag, which delays the successor. Overlapping activities with leads to shorten a plan is fast tracking. A lead is not the same as a start-to-start relationship: both allow overlap, but the lead remains tied to the predecessor's finish.

## In practice

When a corporate film is produced, editing can start before all shooting days are over, because the first scenes are already available. The production manager links “filming” and “editing” with finish-to-start and a lead of three days. The project gains three days but accepts that reshoots may still change the edit.

## Frequently asked questions

### What risk does a lead bring?

The successor starts on an incomplete basis. If the predecessor's result still changes, rework may follow. Leads should therefore only be used where the partial results are stable enough.

### Can a lead be applied to other relationship types?

Yes, in principle to all four. It is most common and easiest to understand, however, with finish-to-start relationships.

## Related terms

- [Lead](https://pmdecoder.com/en/glossary/lead/)
- [Lag](https://pmdecoder.com/en/glossary/lag-pmi/)
- [Logical relationship](https://pmdecoder.com/en/glossary/logical-relationship-pmi/)
- [Finish-to-start](https://pmdecoder.com/en/glossary/finish-to-start/)
- [Fast tracking](https://pmdecoder.com/en/glossary/fast-tracking-pmi/)

---