# Late start date

also: Late start · abbr. LS

- Framework: [cross-framework](https://pmdecoder.com/en/framework/general/)
- Concept: [Latest allowable start of an activity](https://pmdecoder.com/en/concept/latest-allowable-start-of-an-activity/)
- Topic area: [Network planning](https://pmdecoder.com/en/area/network-planning/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/late-start-date/

## Definition

The late start date, LS for short, results from the backward pass by subtracting the duration from the late finish date. If an activity starts after this date and its duration remains unchanged, the project end or a specified interim date moves back. For activities on the critical path, the late start coincides with the early start date.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Late start date](https://pmdecoder.com/en/glossary/late-start-date-pmi/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

The early start date gives the earliest possible start, the late start the last permissible one. Their difference is the total float. If an activity is only started on its late start date, it uses up all its float, and the successors on the same path have correspondingly less room to manoeuvre.

## In practice

A city administration is introducing a new fee regulation at the beginning of the year. The printer needs four weeks for the notices, and dispatch must be completed by mid-December. The backward pass shows that the print order must be placed by 10 November at the latest. The office enters this date as the latest deadline and thus also knows that the council decision must be available by then.

## Frequently asked questions

### What happens if an activity starts after its late start date?

With the same duration, the project end moves back, unless the delay is made up by accelerating other activities.

### Should activities be scheduled on their late start date?

Only for good reason, for example if an early start would tie up material unnecessarily long. Anyone who deliberately starts late gives up any reserve for the unexpected.

## Related terms

- [Late finish date](https://pmdecoder.com/en/glossary/late-finish-date/)
- [Early start date](https://pmdecoder.com/en/glossary/early-start-date/)
- [Backward pass](https://pmdecoder.com/en/glossary/backward-pass/)
- [Total float](https://pmdecoder.com/en/glossary/total-float/)

---