# Late finish date

also: Late finish · abbr. LF

- Framework: [cross-framework](https://pmdecoder.com/en/framework/general/)
- Concept: [Latest allowable finish of an activity](https://pmdecoder.com/en/concept/latest-allowable-finish-of-an-activity/)
- Topic area: [Network planning](https://pmdecoder.com/en/area/network-planning/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/late-finish-date/

## Definition

The late finish date, LF for short, is determined in the backward pass. For the last activity, it is the target date of the project. For all others, it is derived from the earliest of the late start dates of their successors, less any time intervals. It marks the limit by which a piece of work must be done for the overall schedule to hold.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Late finish date](https://pmdecoder.com/en/glossary/late-finish-date-pmi/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

The early finish date gives the earliest possible finish, the late finish the latest permissible one; their difference corresponds to the total float. A contractually agreed delivery date may lie before the calculated late finish and is then decisive as a date constraint.

## In practice

For a wedding reception with 120 guests, an agency plans backwards from the day of the celebration. The table decorations must be in place the evening before, so the flowers must be delivered on the morning of the previous day. Because the florist needs two weeks' notice, the late finish of the order lies two weeks before the celebration. The agency realises that the couple must have chosen the colours by then and schedules a consultation in good time.

## Frequently asked questions

### How is the late finish date calculated?

For finish-to-start relationships, as the smallest late start date of all successors, each less any time interval.

### How does the late finish date differ from a submission deadline?

The late finish is a calculated result from the network schedule, a submission deadline is an agreement. If the agreement is earlier, it applies.

## Related terms

- [Late start date](https://pmdecoder.com/en/glossary/late-start-date/)
- [Early finish date](https://pmdecoder.com/en/glossary/early-finish-date/)
- [Backward pass](https://pmdecoder.com/en/glossary/backward-pass/)
- [Imposed date](https://pmdecoder.com/en/glossary/imposed-date/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.