# Late finish date

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Latest allowable finish of an activity](https://pmdecoder.com/en/concept/latest-allowable-finish-of-an-activity/)
- Topic area: [Network planning](https://pmdecoder.com/en/area/network-planning/)
- Canonical version: https://pmdecoder.com/en/glossary/late-finish-date-pmi/

## Definition

The late finish date, LF for short, is the latest date on which an uncompleted activity may finish without moving the project end or breaching a schedule constraint. It is determined in the backward pass of the critical path method: working back from the project end, it follows from the late start dates of the successors, taking into account relationship type, lag and lead. With several successors, the earliest of these values applies. Together with the early finish date it forms the window in which the activity can finish.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| cross-framework | [Late finish date](https://pmdecoder.com/en/glossary/late-finish-date/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

The late finish date corresponds to the German spätester Endzeitpunkt in network planning. The difference from the early finish date is the total float. A contractually agreed delivery date is an external requirement; the late finish date, by contrast, is a calculated result that can take such a requirement into account.

## In practice

For the introduction of new HR software, go-live at the turn of the year is fixed. The backward pass shows that data cleansing must be completed by 15 November at the latest so that import, testing and approval still fit afterwards. The HR department receives this date as a firm limit and plans its work backwards from it.

## Frequently asked questions

### What does it mean if the late finish date is before the early finish date?

Total float is then negative. The plan cannot meet a constraint, and action is needed, such as schedule compression or moving the imposed date.

### Should activities be allowed to run until their late finish date?

That is risky, because all float is then used up and any further delay hits the project end. It is usually wiser to finish earlier and keep the flexibility as a reserve.

## Related terms

- [Late finish date](https://pmdecoder.com/en/glossary/late-finish-date/)
- [Late start date](https://pmdecoder.com/en/glossary/late-start-date-pmi/)
- [Early finish date](https://pmdecoder.com/en/glossary/early-finish-date-pmi/)
- [Backward pass](https://pmdecoder.com/en/glossary/backward-pass-pmi/)
- [Total float](https://pmdecoder.com/en/glossary/total-float-pmi/)

---