# Iteration

- Framework: [cross-framework](https://pmdecoder.com/en/framework/general/)
- Concept: [Time-boxed work cycle](https://pmdecoder.com/en/concept/time-boxed-work-cycle/)
- Topic area: [Approaches and agility](https://pmdecoder.com/en/area/approaches-and-agility/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/iteration/

## Definition

An iteration is a pass through planning, implementation and review that is repeated at regular intervals. At the end of each pass, an intermediate result is examined, and the insights gained feed into the next pass. Iterations usually last one to four weeks and have a fixed length so that a reliable rhythm develops.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Iteration](https://pmdecoder.com/en/glossary/iteration-pmi/) | equivalent | — |
| Scrum | [Sprint](https://pmdecoder.com/en/glossary/sprint/) | closely related | one month at most, with a Sprint Goal and fixed events; contains all the work up to the Increment |
| Kanban | — | no counterpart | — |

## Distinction

Iterative means improving something in repeated passes, incremental means extending it piece by piece; agile approaches usually combine both. In Scrum, the iteration is called a Sprint. Rolling wave planning refines a plan step by step without necessarily prescribing fixed work cycles.

## In practice

An agency designs a museum's website in two-week iterations. The first produces a clickable sketch of the home page, the second a working exhibition calendar, the third ticket booking. After each iteration, museum staff test the result. Their feedback leads to the search function being implemented earlier than planned, because visitors need it most often.

## Frequently asked questions

### How long should an iteration be?

Short enough to allow rapid feedback and long enough to produce a meaningful intermediate result. Two weeks is a common length.

### May iterations be extended?

Preferably not. A fixed length creates rhythm and makes the team's performance comparable; unfinished work moves into the next iteration.

## Related terms

- [Timeboxing](https://pmdecoder.com/en/glossary/timeboxing/)
- [Agile project management](https://pmdecoder.com/en/glossary/agile-project-management/)
- [Rolling wave planning](https://pmdecoder.com/en/glossary/rolling-wave-planning/)

---