# Iteration

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Time-boxed work cycle](https://pmdecoder.com/en/concept/time-boxed-work-cycle/)
- Topic area: [Approaches and agility](https://pmdecoder.com/en/area/approaches-and-agility/)
- Canonical version: https://pmdecoder.com/en/glossary/iteration-pmi/

## Definition

In PMI usage an iteration is a time-limited cycle of development on a product or deliverable in which all the work needed to deliver value is performed. This includes planning, analysis, design, implementation and testing of a selected slice. Iterations are usually short, often one to four weeks, and follow one another at the same rhythm. At the end there is a result that can be reviewed and on which feedback is gathered; the next iteration is then planned. Iterations are the basic building block of adaptive approaches but also occur in hybrid projects. The fixed length creates a reliable cadence for planning, coordination and delivery.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| cross-framework | [Iteration](https://pmdecoder.com/en/glossary/iteration/) | equivalent | — |
| Scrum | [Sprint](https://pmdecoder.com/en/glossary/sprint/) | closely related | one month at most, with a Sprint Goal and fixed events; contains all the work up to the Increment |
| Kanban | — | no counterpart | — |

## Distinction

The cross-framework term iteration refers to the same thing. The Sprint in Scrum is an iteration with fixed rules, events and a Sprint Goal. A timebox is more general: it limits any kind of activity in time, including a meeting. An iteration differs from a project phase by its short, recurring form.

## In practice

A team builds a customer portal for an electricity supplier in three-week iterations. In the fourth iteration it delivers the consumption display and the invoice download, each tested and made available to the business in a test environment. The business’s comments feed into planning of the fifth iteration.

## Frequently asked questions

### May an iteration be extended if work is left over?

Usually not. The fixed length is precisely the point. Unfinished work is reassessed and, if needed, moved to a later iteration.

### Must every iteration produce something releasable?

The aim is a result that can be tested and assessed. Whether it goes to users immediately is a separate decision about releases.

## Related terms

- [Iteration](https://pmdecoder.com/en/glossary/iteration/)
- [Sprint](https://pmdecoder.com/en/glossary/sprint/)
- [Timebox](https://pmdecoder.com/en/glossary/timebox/)
- [Adaptive approach](https://pmdecoder.com/en/glossary/adaptive-approach/)
- [Burndown chart](https://pmdecoder.com/en/glossary/burndown-chart/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.