# Issues practice

- Framework: [PRINCE2](https://pmdecoder.com/en/framework/prince2/)
- Reference: PRINCE2 7, Praktik Issues
- Edition: PRINCE2 7
- Concept: [Controlled handling of changes](https://pmdecoder.com/en/concept/controlled-handling-of-changes/)
- Topic area: [Monitoring and control](https://pmdecoder.com/en/area/monitoring-and-control/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/issues-practice/

## Definition

The issues practice governs how a PRINCE2 project deals with anything unplanned that needs attention. This includes, for example, requests to change an agreed product, deviations of a product from its specification, and other problems and concerns. Each item is captured, assessed, brought to a decision at the appropriate level and followed up. The practice also covers keeping the status of products and their versions traceable so that changes are made in a controlled way. How this is done in the individual project is described in the issue management approach. The practice replaces the change theme of the 2017 edition and takes a broader view of its subject.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Change control](https://pmdecoder.com/en/glossary/change-control-pmi/) | closely related | emphasizes the review of and decision on change requests, less their implementation |
| cross-framework | [Change control](https://pmdecoder.com/en/glossary/change-control/) | closely related | Covers not only change requests but also deviations from specification, problems and concerns. |

## Other terms

- Change theme (deprecated)

## Distinction

A risk is an uncertain event that may occur; an issue has already occurred or has been raised as a concern. General change management deals with change requests; the issues practice also covers problems, complaints and defects. The issue register under ISO 21506 is a tool, whereas the practice describes the handling as a whole.

## In practice

In a project introducing a new till system, a branch manager reports that vouchers cannot be scanned. The project manager records this as a deviation from the specification and assesses the consequences. Because the fix is possible within the tolerances of the current stage, she decides herself. A second request, to integrate loyalty cards, would break the budget; she refers it to the project board.

## Frequently asked questions

### Who decides on change requests?

In principle, the project board. It can delegate decisions up to an agreed limit to a change authority or to the project manager; this arrangement is recorded in the issue management approach.

### Does every issue have to be recorded formally?

No. The project manager can also resolve minor points informally and simply note them. What needs assessment, a decision or follow-up is recorded formally.

## Related terms

- [Issue Management Approach](https://pmdecoder.com/en/glossary/issue-management-approach/)
- [Issue](https://pmdecoder.com/en/glossary/issue/)
- [Change control](https://pmdecoder.com/en/glossary/change-control/)
- [Change request](https://pmdecoder.com/en/glossary/change-request/)
- [Configuration management](https://pmdecoder.com/en/glossary/configuration-management/)
- [Issue Register](https://pmdecoder.com/en/glossary/issue-register-prince2/)
- [Issue Report](https://pmdecoder.com/en/glossary/issue-report/)
- [Change Authority](https://pmdecoder.com/en/glossary/change-authority/)

---