# Issue

- Framework: [ISO 21506](https://pmdecoder.com/en/framework/iso-21506/)
- Reference: ISO 21506:2024, 3.31
- Edition: ISO 21506:2024
- Concept: [Occurring problem that needs resolution](https://pmdecoder.com/en/concept/occurring-problem-that-needs-resolution/)
- Topic area: [Monitoring and control](https://pmdecoder.com/en/area/monitoring-and-control/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/issue/

## Definition

An issue is something that has already happened and needs to be resolved: a missing decision, a technical problem, a conflict between stakeholders or contradictory requirements. Issues are kept in a register with a description, owner, priority, target date and status, and reviewed regularly until they are closed.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Issue](https://pmdecoder.com/en/glossary/issue-pmi/) | equivalent | — |

## Distinction

A risk may occur, whereas an issue is already there; when a risk occurs, it becomes an issue. A task is planned work, whereas an issue is an unexpected matter to be clarified. ISO 21506 calls the corresponding list the issue register; in practice it is also known as an issue log.

## In practice

While building a citizen services portal, the team discovers that two departments require different mandatory fields for the same form. The question is added to the issue register, owned by the sub-project manager for forms, with a target date two weeks away. Because it cannot be resolved by then, the project manager escalates it to the steering committee, which decides on a uniform rule. The decision and its date remain documented in the register.

## Frequently asked questions

### How do you tell issues from risks?

By asking whether it has already happened. Uncertain events belong in the risk register, events that have occurred in the issue register.

### When must an issue be escalated?

When it cannot be resolved within the project, misses its target date or significantly jeopardizes schedule, cost or quality.

## Related terms

- [Issue register](https://pmdecoder.com/en/glossary/issue-register/)
- [Risk](https://pmdecoder.com/en/glossary/risk/)
- [Meeting minutes](https://pmdecoder.com/en/glossary/meeting-minutes/)
- [Progress report](https://pmdecoder.com/en/glossary/progress-report/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.