# Issue register

- Framework: [ISO 21506](https://pmdecoder.com/en/framework/iso-21506/)
- Reference: ISO 21506:2024, 3.32
- Edition: ISO 21506:2024
- Concept: [Register of issues](https://pmdecoder.com/en/concept/register-of-issues/)
- Topic area: [Monitoring and control](https://pmdecoder.com/en/area/monitoring-and-control/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/issue-register/

## Definition

The issue register is the working tool for everything that has already happened in the project and needs to be resolved. Each entry describes the issue, its effects and its priority, names an owner and a target date, and documents the agreed actions, decisions and current status. It is reviewed in regular meetings; closed issues remain in the register together with their resolution.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Issue log](https://pmdecoder.com/en/glossary/issue-log/) | equivalent | — |
| PRINCE2 | [Issue Register](https://pmdecoder.com/en/glossary/issue-register-prince2/) | closely related | Holds only issues handled formally; informally handled matters are kept in the Daily Log. Requests for change are one type of issue. |

## Distinction

The risk register contains events that might occur, the issue register those that already have. A task list manages planned work, the issue register unexpected matters that need clarifying. The change register records changes to the agreed undertaking, which often, but not always, result from issues.

## In practice

During the commissioning of a wastewater treatment plant, site management keeps an issue register that most recently contains 64 entries, ranging from missing test certificates to a pump that shuts down during heavy rain. Every Tuesday, site management, the manufacturer and the operator go through the register. High-priority issues that see no progress for two weeks are reported to the project manager. At acceptance, the register serves as evidence of which defects have been remedied.

## Frequently asked questions

### What belongs in an issue register?

At least an identifier, description, date raised, priority, owner, target date, actions and status. Many projects add the effects on schedule and cost.

### When is an issue closed?

When the agreed resolution has been implemented and confirmed by the person who raised the issue or who is responsible for it. The closure is documented with its date.

## Related terms

- [Issue](https://pmdecoder.com/en/glossary/issue/)
- [Risk register](https://pmdecoder.com/en/glossary/risk-register/)
- [Change register](https://pmdecoder.com/en/glossary/change-register/)
- [Meeting minutes](https://pmdecoder.com/en/glossary/meeting-minutes/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.