# Issue Register

- Framework: [PRINCE2](https://pmdecoder.com/en/framework/prince2/)
- Reference: PRINCE2 7, Praktik Issues
- Edition: PRINCE2 7
- Concept: [Register of issues](https://pmdecoder.com/en/concept/register-of-issues/)
- Topic area: [Monitoring and control](https://pmdecoder.com/en/area/monitoring-and-control/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/issue-register-prince2/

## Definition

In PRINCE2 the Issue Register is the record of the issues that the project handles formally. An issue is an event that has happened, was not planned and requires a decision or action from project management. PRINCE2 distinguishes three types: a request for change to an agreed baseline, an off-specification, where a product does not or is forecast not to meet its specification, and a problem/concern covering all other matters. Each entry receives an identifier, the type, a description, ratings for priority and severity, the status and the date of closure. The register is created during initiation; how issues are captured, assessed and decided is set out in the issue management approach.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | [Issue register](https://pmdecoder.com/en/glossary/issue-register/) | closely related | Holds only issues handled formally; informally handled matters are kept in the Daily Log. Requests for change are one type of issue. |
| PMI / PMBOK Guide | [Issue log](https://pmdecoder.com/en/glossary/issue-log/) | closely related | Holds only issues handled formally; informally handled matters are kept in the Daily Log. Requests for change are one type of issue. |

## Distinction

The Issue Register corresponds to the issue register in ISO 21506 and the PMI Issue Log, but is narrower in scope: matters that can be dealt with informally are kept by the Project Manager in the Daily Log. A change request is not a separate list in PRINCE2 but one type of issue. It differs from the Risk Register in that the events have already occurred. Where an issue needs more detailed examination, the entry refers to an Issue Report.

## In practice

In a project for a new customer portal, the sales team reports that an English language version is also needed. The project manager records this as a request for change in the Issue Register. Shortly afterwards a test shows that the loading time of the home page exceeds the agreed limit; this is entered as an off-specification. Both receive a priority, and for the request for change the project manager prepares an Issue Report as the basis for a decision.

## Frequently asked questions

### Which types of issue does PRINCE2 recognize?

Three types: a request for change to something already agreed or approved, an off-specification where a product departs from its specification, and, as a catch-all, any other problem or concern that project management has to resolve.

### Does every issue have to go into the Issue Register?

No. Anything that can be settled without a formal procedure is noted by the Project Manager in the Daily Log. The Issue Register holds the issues that need to be assessed, decided and tracked.

## Related terms

- [Issue register](https://pmdecoder.com/en/glossary/issue-register/)
- [Issue log](https://pmdecoder.com/en/glossary/issue-log/)
- [Issue](https://pmdecoder.com/en/glossary/issue/)
- [Issue Report](https://pmdecoder.com/en/glossary/issue-report/)
- [Daily Log](https://pmdecoder.com/en/glossary/daily-log/)
- [Change request](https://pmdecoder.com/en/glossary/change-request/)
- [Issue Management Approach](https://pmdecoder.com/en/glossary/issue-management-approach/)
- [Issues practice](https://pmdecoder.com/en/glossary/issues-practice/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.
