# Issue

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Occurring problem that needs resolution](https://pmdecoder.com/en/concept/occurring-problem-that-needs-resolution/)
- Topic area: [Monitoring and control](https://pmdecoder.com/en/area/monitoring-and-control/)
- Canonical version: https://pmdecoder.com/en/glossary/issue-pmi/

## Definition

In PMI usage, an issue is a circumstance that already exists and can affect the project objectives. Typical issues are an unresolved conflict between requirements, a failed supplier, a disagreement between stakeholders or a missing decision. Every issue needs an owner, a target date for resolution and an assessment of its urgency. Issues are recorded and tracked in the issue log. Unresolved issues can trigger change requests, corrective actions or escalation to the sponsor or governing body.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | [Issue](https://pmdecoder.com/en/glossary/issue/) | equivalent | — |

## Distinction

In substance the term matches the ISO 21506 term issue. The key distinction is from risk: a risk is an uncertain event that may occur, whereas an issue has already occurred or already exists. When a risk materializes, it becomes an issue. A workaround is an unplanned response to a problem that has occurred, while the issue is the situation itself. In everyday use, “issue” also refers to tickets in software development tools, which is broader than the PMI term.

## In practice

While introducing a new point-of-sale system, the team finds that two branches use older network equipment on which the software does not run. The project manager enters the issue in the issue log with a description, its impact on the roll-out date, an owner from IT infrastructure and a target date. In the weekly status meeting it is decided to switch the two branches over later and to replace the network equipment first.

## Frequently asked questions

### When does a risk become an issue?

As soon as the event described has occurred or is certain to occur. The entry in the risk register is then closed or flagged and followed up as an issue, often with the previously planned contingency plan as the first action.

### Does every small problem need to be logged as an issue?

No. Anything the team resolves immediately within its authority needs no entry. Issues are logged when they affect objectives, schedule or cost, require a decision or cannot be resolved quickly.

## Related terms

- [Issue](https://pmdecoder.com/en/glossary/issue/)
- [Issue log](https://pmdecoder.com/en/glossary/issue-log/)
- [Risk](https://pmdecoder.com/en/glossary/risk-pmi/)
- [Corrective action](https://pmdecoder.com/en/glossary/corrective-action-pmi/)
- [Workaround](https://pmdecoder.com/en/glossary/workaround-pmi/)
- [Root cause analysis](https://pmdecoder.com/en/glossary/root-cause-analysis-pmi/)

---