# Issue Management Approach

- Framework: [PRINCE2](https://pmdecoder.com/en/framework/prince2/)
- Reference: PRINCE2 7, Praktik Issues
- Edition: PRINCE2 7
- Concept: [Controlled handling of changes](https://pmdecoder.com/en/concept/controlled-handling-of-changes/)
- Topic area: [Monitoring and control](https://pmdecoder.com/en/area/monitoring-and-control/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/issue-management-approach/

## Definition

The issue management approach describes how a PRINCE2 project puts the issues practice into effect. It specifies which types of issue are distinguished, how they are captured and assessed, who may decide on changes up to which limit and how decisions are documented. It also governs how products and their versions are managed, so that it is always clear which state applies. This includes details of tools, registers, reports and priorities. The approach is created during initiation and becomes part of the project initiation documentation. In the 2017 edition, these questions were covered by a management product called the change control approach.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Change control](https://pmdecoder.com/en/glossary/change-control-pmi/) | partially overlapping | Document setting out the rules for issues and changes in one project, not the activity itself. |
| cross-framework | [Change control](https://pmdecoder.com/en/glossary/change-control/) | partially overlapping | Document setting out the rules for issues and changes in one project, not the activity itself. |

## Distinction

The issues practice describes the general procedure, the issue management approach its design in the individual project. The issue register contains the individual entries, the approach the rules for them. In the PMI world, the content is spread across the change management plan and the configuration management plan.

## In practice

A software firm is developing an app for a bank. The issue management approach specifies that change requests of up to three person-days are decided by the project manager, larger ones by a change authority made up of the product owner and senior user, and anything exceeding the stage budget by the project board. Released versions are tagged in the repository and noted in a version overview.

## Frequently asked questions

### Why is a separate approach needed for issues?

Because otherwise it is unclear in each case who may decide. Fixed rules prevent changes from creeping in uncontrolled or important decisions from being left pending.

### What is a change authority?

A person or group to whom the project board delegates decisions on changes up to an agreed limit. The issue management approach names them and their powers.

## Related terms

- [Issues practice](https://pmdecoder.com/en/glossary/issues-practice/)
- [Change control](https://pmdecoder.com/en/glossary/change-control/)
- [Change control](https://pmdecoder.com/en/glossary/change-control-pmi/)
- [Configuration management](https://pmdecoder.com/en/glossary/configuration-management/)
- [Issue register](https://pmdecoder.com/en/glossary/issue-register/)
- [Issue Register](https://pmdecoder.com/en/glossary/issue-register-prince2/)
- [Issue Report](https://pmdecoder.com/en/glossary/issue-report/)
- [Change Authority](https://pmdecoder.com/en/glossary/change-authority/)

---