# Integrated baseline review

abbr. IBR

- Framework: [ISO 21506](https://pmdecoder.com/en/framework/iso-21506/)
- Reference: ISO 21506:2024, 3.30
- Edition: ISO 21506:2024
- Topic area: [Monitoring and control](https://pmdecoder.com/en/area/monitoring-and-control/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/integrated-baseline-review/

## Definition

An integrated baseline review takes place once the performance measurement baseline has been set up, and often again after major changes. The client, the project manager and the control account managers work through together whether all of the technical content is covered, whether schedules, budgets and resources fit together and whether risks have been taken into account. The aim is for everyone involved to read the baseline in the same way before variances against it are reported.

## Equivalents in other frameworks

No equivalents have been recorded for this term yet.

## Distinction

An audit checks whether processes and requirements are being followed. An integrated baseline review examines the content of a specific plan and ends with jointly agreed actions. It differs from a project approval in that it does not decide whether the project goes ahead but secures the basis for measurement.

## In practice

Three months after the contract for a shipbuilding project begins, representatives of the navy and the shipyard meet for a two-day integrated baseline review. Interviews with eight control account managers reveal that the integration of the weapon systems appears in the schedule but has no budget for testing. The shipyard adds a work package and adjusts the baseline before the first formal performance report is issued.

## Frequently asked questions

### Who takes part in an integrated baseline review?

Representatives of the client, the project manager and the people who own control accounts. Specialists in scheduling, cost and risk often join them.

### Is the review only common in public contracts?

It is most widespread in large public programmes that use earned value management, for example in defence and space. The idea of reviewing a baseline jointly before measuring against it can, however, be applied to any larger project.

## Related terms

- [Performance measurement baseline](https://pmdecoder.com/en/glossary/performance-measurement-baseline/)
- [Earned value management planning](https://pmdecoder.com/en/glossary/earned-value-management-planning/)
- [Control account](https://pmdecoder.com/en/glossary/control-account/)
- [Baseline](https://pmdecoder.com/en/glossary/baseline/)
- [Project audit](https://pmdecoder.com/en/glossary/project-audit/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.