# Initiating a project

- Framework: [PRINCE2](https://pmdecoder.com/en/framework/prince2/)
- Reference: PRINCE2 7, Prozesse
- Edition: PRINCE2 7
- Concept: [Opening stage of a project](https://pmdecoder.com/en/concept/opening-stage-of-a-project/)
- Topic area: [Initiating](https://pmdecoder.com/en/area/initiating/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/initiating-a-project/

## Definition

Initiating a project forms the initiation stage in PRINCE2, that is, the first management stage. In this process the project manager prepares the foundations on which the Project Board decides whether the project should go ahead. These include tailoring the method to the project, the approaches to quality, risk, change and communication, the project controls, the project plan and a detailed business case. The results are brought together in the project initiation documentation, which serves as the reference for what was agreed and is updated at stage boundaries.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PM² | [Initiating Phase](https://pmdecoder.com/en/glossary/initiating-phase/) | closely related | ends with the Ready for Planning phase gate and delivers the Business Case and Project Charter |
| Six Sigma | [Define phase](https://pmdecoder.com/en/glossary/define-phase/) | closely related | First phase of an improvement project; more narrowly focused on the problem, a measurable output and customer requirements than general initiation. |
| cross-framework | [Project initiation](https://pmdecoder.com/en/glossary/project-initiation/) | closely related | Forms the first management stage and ends with authorization of the project by the Project Board; the pre-project check comes before it. |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

The initiating phase in PM² and general project initiation cover similar tasks. PRINCE2 separates them from the short start-up that precedes the project. The initiation stage, by contrast, is already part of the project and is explicitly authorized and funded by the Project Board.

## In practice

After authorization, the project manager of a university project for a new campus management system spends six weeks preparing the plans. She defines how change requests from the faculties will be handled, how often progress will be reported and which stages are planned. The Project Board reviews the documents and authorizes the project and the first delivery stage.

## Frequently asked questions

### What happens if the Project Board does not authorize the project after initiation?

The project is then closed in an orderly way. Initiation has served its purpose in that case, because it prevented a costly wrong decision.

### Is initiation necessary with an agile approach?

Yes, but it can be leaner. Agile projects also need a justification, controls and a shared understanding of the objective.

## Related terms

- [Starting up a project](https://pmdecoder.com/en/glossary/starting-up-a-project/)
- [Directing a project](https://pmdecoder.com/en/glossary/directing-a-project/)
- [Project initiation](https://pmdecoder.com/en/glossary/project-initiation/)
- [Initiating Phase](https://pmdecoder.com/en/glossary/initiating-phase/)
- [Project plan](https://pmdecoder.com/en/glossary/project-plan-iso/)
- [Project Initiation Documentation](https://pmdecoder.com/en/glossary/project-initiation-documentation/)
- [Project Brief](https://pmdecoder.com/en/glossary/project-brief/)
- [Business Case](https://pmdecoder.com/en/glossary/business-case-prince2/)

---