# Highlight Report

- Framework: [PRINCE2](https://pmdecoder.com/en/framework/prince2/)
- Reference: PRINCE2 7, Praktik Fortschritt
- Edition: PRINCE2 7
- Concept: [Regular project status report](https://pmdecoder.com/en/concept/regular-project-status-report/)
- Topic area: [Stakeholders and communication](https://pmdecoder.com/en/area/stakeholders-and-communication/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/highlight-report/

## Definition

In PRINCE2 the Highlight Report is the Project Manager’s regular status report to the Project Board. It enables the Board to direct the project by exception: as long as the reports show that the stage is running within its tolerances, the Board need not intervene or hold meetings. The report summarizes what was achieved in the reporting period, what is planned for the next period, how time, cost, scope and quality stand against the tolerances, which significant issues and risks exist, and which changes have been approved or proposed. Frequency, format and distribution are set during initiation and in the stage plans. Further recipients, such as stakeholders outside the Board, are possible.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | [Progress report](https://pmdecoder.com/en/glossary/progress-report/) | closely related | Report from the Project Manager to the Project Board per management stage, geared to management by exception. |
| PM² | [Project Progress Report](https://pmdecoder.com/en/glossary/project-progress-report/) | closely related | defined PM² artefact from the Project Manager to the Project Steering Committee |

## Distinction

The Highlight Report corresponds to the progress report in ISO 21506 and the PM² Project Progress Report, but is explicitly geared to direction by the Project Board under management by exception. The Checkpoint Report reports one level lower, from the team to the Project Manager. If a tolerance breach is forecast, the Highlight Report is not enough; an Exception Report follows.

## In practice

In a project to renew the network equipment at twelve school sites, the Project Board receives a Highlight Report every two weeks. The latest report states that eight sites have been switched over, costs are on plan and the schedule is five days behind target but still within tolerance. It lists supply shortages for switches as a risk. The Board takes note of the report without calling a meeting.

## Frequently asked questions

### How often is a Highlight Report produced?

At the intervals set by the Project Board, often every one to four weeks. The frequency can differ from stage to stage and depends on the risk and pace of the project.

### Does the Highlight Report replace Project Board meetings?

Largely, yes. PRINCE2 intends the Board to be kept informed through reports and to meet only at fixed decision points or in exception situations. Informal conversations are not affected.

## Related terms

- [Checkpoint Report](https://pmdecoder.com/en/glossary/checkpoint-report/)
- [Progress report](https://pmdecoder.com/en/glossary/progress-report/)
- [Project Progress Report](https://pmdecoder.com/en/glossary/project-progress-report/)
- [Exception Report](https://pmdecoder.com/en/glossary/exception-report/)
- [Steering committee](https://pmdecoder.com/en/glossary/steering-committee/)
- [Project Board](https://pmdecoder.com/en/glossary/project-board/)
- [Controlling a stage](https://pmdecoder.com/en/glossary/controlling-a-stage/)
- [Communication Management Approach](https://pmdecoder.com/en/glossary/communication-management-approach/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.