# Hierarchical decomposition

- Framework: [ISO 21506](https://pmdecoder.com/en/framework/iso-21506/)
- Reference: ISO 21506:2024, 3.29
- Edition: ISO 21506:2024
- Topic area: [Planning and project structure](https://pmdecoder.com/en/area/planning-and-project-structure/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/hierarchical-decomposition/

## Definition

Hierarchical decomposition starts with the entire scope of a project or programme and splits it into a few large parts, which are in turn broken down into smaller ones. This creates a tree structure in which every element has exactly one parent. It ends when the lowest elements are small enough to be estimated, owned and controlled. The breakdown can follow results, phases or organizational units, but each level should follow a single criterion.

## Equivalents in other frameworks

No equivalents have been recorded for this term yet.

## Distinction

Decomposition is the umbrella term for any step-by-step refinement, including by function or other criteria. Hierarchical decomposition is the form that produces a work breakdown structure, and it follows the 100 % rule. A network schedule, by contrast, shows dependencies between activities rather than relationships between a whole and its parts.

## In practice

An association is organizing a trade fair. At the first level, the team divides the work into exhibitor services, supporting programme, hall logistics, marketing and project management. Hall logistics is further divided into stand construction, technology, security and cleaning, and security into first aid, stewarding and fire safety. After four levels, all elements are small enough to be contracted and budgeted individually. Only the expensive stand construction is broken down one level further.

## Frequently asked questions

### How many levels are usual?

That depends on size and complexity. Smaller projects often manage with three levels, large projects have more. Not every branch has to be broken down to the same depth.

### By what criterion is the first level structured?

Often by the most important results, because this makes the scope most visible. Structuring by phase is also common but often makes it harder to assign responsibility.

## Related terms

- [Decomposition](https://pmdecoder.com/en/glossary/decomposition/)
- [Work breakdown structure](https://pmdecoder.com/en/glossary/work-breakdown-structure/)
- [100 % rule](https://pmdecoder.com/en/glossary/100-percent-rule/)
- [Work breakdown structure element](https://pmdecoder.com/en/glossary/work-breakdown-structure-element/)
- [Parent element](https://pmdecoder.com/en/glossary/parent-element/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.