# Governance

- Framework: [ISO 21506](https://pmdecoder.com/en/framework/iso-21506/)
- Reference: ISO 21506:2024, 3.27
- Edition: ISO 21506:2024
- Concept: [Framework for direction, decisions and oversight](https://pmdecoder.com/en/concept/framework-for-direction-decisions-and-oversight/)
- Topic area: [Project organization](https://pmdecoder.com/en/area/project-organization/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/governance/

## Definition

Governance answers the question of who in an organization may decide what, according to which rules and to whom they are answerable for it. It includes fundamental values and principles, binding policies, decision-making bodies with their powers, and procedures for oversight and reporting. For projects, programmes and portfolios it is the outer framework: it determines how undertakings are approved, supervised and ended.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Governance](https://pmdecoder.com/en/glossary/governance-pmi/) | equivalent | — |

## Other terms

- Corporate governance (related, not equivalent)

## Distinction

Management acts within the framework, governance sets and oversees it. Project governance applies this idea to individual projects. Compliance, meaning adherence to laws and internal rules, is part of governance but not the whole of it.

## In practice

After several failed IT undertakings, an insurance group reorganizes its governance. The board decides that undertakings over five million euros will only be approved with a reviewed business case, that an investment committee will report on the portfolio every quarter and that every project will have a named sponsor from senior management. Internal audit checks every year whether these rules are being followed.

## Frequently asked questions

### Is governance only something for large companies?

No. Small organizations also have rules about who decides and who oversees, often unwritten ones. As size and responsibility grow, it becomes worthwhile to set them down explicitly.

### How are governance and project management related?

Governance sets the conditions under which projects come about, who approves them and how they are reported on. Within these conditions, project management ensures that the projects achieve their objectives.

## Related terms

- [Governing body](https://pmdecoder.com/en/glossary/governing-body/)
- [Project governance](https://pmdecoder.com/en/glossary/project-governance/)
- [Portfolio management](https://pmdecoder.com/en/glossary/portfolio-management/)
- [Steering committee](https://pmdecoder.com/en/glossary/steering-committee/)

---