# Free float

also: Free slack

- Framework: [cross-framework](https://pmdecoder.com/en/framework/general/)
- Concept: [Scheduling flexibility relative to successors](https://pmdecoder.com/en/concept/scheduling-flexibility-relative-to-successors/)
- Topic area: [Network planning](https://pmdecoder.com/en/area/network-planning/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/free-float/

## Definition

Free float measures the latitude of an activity in relation to its direct successors. It is the difference between the early start date of the successor that starts earliest and the early finish date of the activity, less any time interval where applicable. Anyone who uses their free float does not affect anyone else in the plan.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Free float](https://pmdecoder.com/en/glossary/free-float-pmi/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Classification

- Broader term: [Float](https://pmdecoder.com/en/glossary/float/)

## Distinction

Total float relates to the project end and may be shared with other activities, whereas free float belongs to the activity alone. It is therefore always less than or equal to total float. DIN 69900 recognises further types of float, such as independent float, which are rarely used in practice.

## In practice

When an exhibition stand is being set up, the activity "Pre-assemble lighting" has three days of free float because the subsequent installation has to wait for the ceiling structure anyway. The electrician can therefore start two days later without consulting anyone, in order to finish an urgent job first. If the activity had only total float but no free float, she would have to coordinate the postponement with the ceiling contractor.

## Frequently asked questions

### How is free float calculated?

For finish-to-start relationships, as the smallest early start of all successors minus the early finish of the activity. Time intervals and other types of relationship are taken into account accordingly.

### Why is free float useful in day-to-day work?

It shows where those responsible can decide for themselves without affecting others. This saves coordination.

## Related terms

- [Total float](https://pmdecoder.com/en/glossary/total-float/)
- [Successor activity](https://pmdecoder.com/en/glossary/successor-activity/)
- [Early finish date](https://pmdecoder.com/en/glossary/early-finish-date/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.