# Free float

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Scheduling flexibility relative to successors](https://pmdecoder.com/en/concept/scheduling-flexibility-relative-to-successors/)
- Topic area: [Network planning](https://pmdecoder.com/en/area/network-planning/)
- Canonical version: https://pmdecoder.com/en/glossary/free-float-pmi/

## Definition

Free float is the flexibility an activity has with respect to its immediate successors. It indicates how far the activity can move or extend without any successor having to start later than its early start date and without violating a schedule constraint. It is calculated from the gap between the early finish date of the activity and the early start of the following activity, or the smallest gap where there are several successors. Free float can never be greater than total float.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| cross-framework | [Free float](https://pmdecoder.com/en/glossary/free-float/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

Free float corresponds to the German freier Puffer in network planning. Total float relates to the project end: using it up does not threaten the end date but removes flexibility from subsequent activities. Free float, by contrast, can be consumed without affecting any other activity. A deliberately planned time reserve is not float but a buffer in the sense of a reserve.

## In practice

In a conversion project, electrical installation in the annex has five days of total float but only two days of free float, because drywall work follows immediately. When the electrician asks for three more days, the project manager knows that the end date will hold but the drywall contractor will have to start one day later, and agrees the dates with both firms.

## Frequently asked questions

### Why is free float useful for control?

It shows which delays do not trigger a chain reaction. Within free float, the project manager can move dates without having to inform other parties.

### Do activities on the critical path have free float?

Usually not. Because they have no total float and free float cannot be larger, their free flexibility is also zero.

## Related terms

- [Free float](https://pmdecoder.com/en/glossary/free-float/)
- [Total float](https://pmdecoder.com/en/glossary/total-float-pmi/)
- [Successor activity](https://pmdecoder.com/en/glossary/successor-activity-pmi/)
- [Early start date](https://pmdecoder.com/en/glossary/early-start-date-pmi/)
- [Critical path method](https://pmdecoder.com/en/glossary/critical-path-method-pmi/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.