# Forward pass

also: Forward pass calculation

- Framework: [cross-framework](https://pmdecoder.com/en/framework/general/)
- Concept: [Calculation of earliest dates](https://pmdecoder.com/en/concept/calculation-of-earliest-dates/)
- Topic area: [Network planning](https://pmdecoder.com/en/area/network-planning/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/forward-pass/

## Definition

The forward pass begins at the start activity and works step by step through the network schedule. Each activity receives an early start date, derived from the dates of its predecessors and any time intervals, and an early finish date calculated as start plus duration. Where several predecessors converge, the one that finishes last determines the start. At the end activity, the result is the earliest possible project completion.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Forward pass](https://pmdecoder.com/en/glossary/forward-pass-pmi/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

The backward pass works the other way round, from the project end to the start, and provides the latest dates. Only the two calculations together yield float and the critical path. The forward pass therefore answers when the project can be finished at the earliest, but not which activities are decisive for this.

## In practice

A project starts on day 0 with activity A, which takes four days. A is followed by B with six days and C with three days; D, with two days, needs both B and C. The forward pass shows that A finishes on day 4 at the earliest, B on day 10 and C on day 7. D has to wait for B, so it starts on day 10 at the earliest and finishes on day 12. The project can therefore be completed after twelve days at the earliest.

## Frequently asked questions

### Why does the predecessor that finishes last determine the start?

Because a successor can only start once all its predecessors are complete. The decisive one is therefore the predecessor that finishes last.

### Do you count from day 0 or from day 1?

Both are common. What matters is to apply one counting convention consistently, because otherwise dates shift by one day.

## Related terms

- [Backward pass](https://pmdecoder.com/en/glossary/backward-pass/)
- [Early start date](https://pmdecoder.com/en/glossary/early-start-date/)
- [Early finish date](https://pmdecoder.com/en/glossary/early-finish-date/)
- [Critical path](https://pmdecoder.com/en/glossary/critical-path/)

---