# Forward pass

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Calculation of earliest dates](https://pmdecoder.com/en/concept/calculation-of-earliest-dates/)
- Topic area: [Network planning](https://pmdecoder.com/en/area/network-planning/)
- Canonical version: https://pmdecoder.com/en/glossary/forward-pass-pmi/

## Definition

The forward pass is the first calculation step of the critical path method. Starting from the project start or the data date of the calculation, the network is traversed in the direction of the dependencies to determine the early start date and early finish date of each open activity. The early start of an activity follows from the early finish dates of its predecessors, taking into account relationship type, lag and lead; with several predecessors, the latest value governs. The early finish date of the last activity shows the earliest date on which the project can end.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| cross-framework | [Forward pass](https://pmdecoder.com/en/glossary/forward-pass/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

The forward pass corresponds to the German Vorwärtsrechnung in network planning. It yields the early dates; the late dates, and with them the float, only follow from the subsequent backward pass. A rough schedule estimate without network logic, such as adding up phase durations, is not a forward pass in the proper sense.

## In practice

A club is planning a summer party. The permit takes four weeks; after that, the marquee hire and catering can be booked in parallel, taking two and three weeks respectively. The forward pass shows that set-up can start after seven weeks at the earliest, because it waits for both bookings. The party is therefore possible in eight weeks at the earliest.

## Frequently asked questions

### What is needed for a forward pass?

A complete list of activities with durations, the logical relationships between them and a starting point. If dependencies are missing, the calculated early dates are too optimistic.

### How does a lag affect the forward pass?

It moves the early start of the successor back by the length of the waiting time. A lead has the opposite effect and brings the start forward.

## Related terms

- [Forward pass](https://pmdecoder.com/en/glossary/forward-pass/)
- [Backward pass](https://pmdecoder.com/en/glossary/backward-pass-pmi/)
- [Early start date](https://pmdecoder.com/en/glossary/early-start-date-pmi/)
- [Early finish date](https://pmdecoder.com/en/glossary/early-finish-date-pmi/)
- [Critical path method](https://pmdecoder.com/en/glossary/critical-path-method-pmi/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.
