# Forecast

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Estimate of final dates and costs](https://pmdecoder.com/en/concept/estimate-of-final-dates-and-costs/)
- Topic area: [Monitoring and control](https://pmdecoder.com/en/area/monitoring-and-control/)
- Canonical version: https://pmdecoder.com/en/glossary/forecast/

## Definition

In PMI usage, a forecast is an assessment of how a project is likely to develop, based on the information available when it is prepared. It typically concerns cost, schedule, resource needs or the achievable scope. Forecasts are updated regularly during execution as new performance data become available. They can be based on earned value indicators, trend observations, re-estimates of the remaining work or, in agile approaches, a team's throughput so far. A forecast is not a commitment but a reasoned expectation that prepares decisions.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| cross-framework | [Project forecast](https://pmdecoder.com/en/glossary/project-forecast/) | closely related | can refer to any future quantity, not only the finish date and final cost |

## Distinction

The closest cross-framework term for the concept is project forecast. The PMI term is somewhat broader because it covers not only the final date and final cost but any outlook on future conditions and events. An estimate usually concerns a single quantity before or during planning, whereas a forecast condenses the current status into a statement about the end. Estimate at completion and estimate to complete are specific forms of a cost forecast.

## In practice

In a construction project for a logistics centre, project controls produce a forecast every month. Schedule and progress data show that handover is likely to be three weeks later than planned, and total cost is expected to be four percent over budget. The forecast states its assumptions, such as the delivery time of the conveyor system, and gives a range. On this basis the steering committee decides on additional shifts.

## Frequently asked questions

### How often should a forecast be updated?

In line with the performance measurement cycle, usually monthly or at the end of each iteration. It is updated outside that cycle when an event significantly changes the assumptions, such as a supplier failure.

### Should a forecast be a single value or a range?

A range with the key assumptions is more honest, because every forecast is uncertain. Reports often also give a most likely value so that decision-makers have a clear point of reference.

## Related terms

- [Project forecast](https://pmdecoder.com/en/glossary/project-forecast/)
- [Estimate at completion](https://pmdecoder.com/en/glossary/estimate-at-completion-pmi/)
- [Estimate to complete](https://pmdecoder.com/en/glossary/estimate-to-complete-pmi/)
- [Trend analysis](https://pmdecoder.com/en/glossary/trend-analysis-pmi/)
- [Earned value management](https://pmdecoder.com/en/glossary/earned-value-management-pmi/)

---