# Focus on products principle

- Framework: [PRINCE2](https://pmdecoder.com/en/framework/prince2/)
- Reference: PRINCE2 7, Grundprinzipien
- Edition: PRINCE2 7
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/focus-on-products-principle/

## Definition

The focus on products principle requires a PRINCE2 project to establish first what it is to deliver and only then which activities are needed to deliver it. Products are all outputs, tangible or intangible, including the documents used to manage the project. For each significant product the team describes its purpose, its composition and the quality criteria against which it will be judged. These descriptions form the basis for planning, estimating, work allocation, quality checking and acceptance. The principle is meant to prevent stakeholders from holding different ideas about the result and to avoid work that contributes nothing recognizable to it.

## Equivalents in other frameworks

No equivalents have been recorded for this term yet.

## Distinction

A work breakdown structure often breaks down the work; PRINCE2 starts from the results with a product breakdown structure and derives the work from it. The term product is broader in PRINCE2 than in everyday language and is closer to deliverable. The principle shares only the word with the Scrum Product Owner.

## In practice

For the redesign of a museum gallery, the team first defines the products: spatial concept, exhibition texts, media stations, lighting and step-free visitor routes. For the media stations, for instance, it is stated that they must be usable without instructions and available in two languages. Only then are work steps, responsibilities and dates planned.

## Frequently asked questions

### Are reports and plans also products in PRINCE2?

Yes. PRINCE2 distinguishes management products, which serve to run the project, from specialist products, which are handed over to users.

### What does the product view achieve in practice?

It clarifies early what counts as finished. Effort can be estimated more reliably, and disputes at acceptance become rarer because the criteria were agreed beforehand.

## Related terms

- [Product breakdown structure](https://pmdecoder.com/en/glossary/product-breakdown-structure/)
- [Deliverable](https://pmdecoder.com/en/glossary/deliverable/)
- [Acceptance criteria](https://pmdecoder.com/en/glossary/acceptance-criteria/)
- [Managing product delivery](https://pmdecoder.com/en/glossary/managing-product-delivery/)
- [Project scope](https://pmdecoder.com/en/glossary/project-scope/)
- [Product Description](https://pmdecoder.com/en/glossary/product-description/)
- [Product Breakdown Structure](https://pmdecoder.com/en/glossary/product-breakdown-structure-prince2/)
- [Project Product Description](https://pmdecoder.com/en/glossary/project-product-description/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.