# Float

also: Slack

- Framework: [cross-framework](https://pmdecoder.com/en/framework/general/)
- Topic area: [Network planning](https://pmdecoder.com/en/area/network-planning/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/float/

## Definition

Float is the scheduling latitude of an activity in the network schedule. It arises when an activity can be finished earlier than its successors or the end date require. The main distinction is between total float, which relates to the project end, and free float, which relates to the immediate successors. Activities without total float lie on the critical path.

## Equivalents in other frameworks

No equivalents have been recorded for this term yet.

## Classification

- Narrower terms: [Free float](https://pmdecoder.com/en/glossary/free-float/), [Total float](https://pmdecoder.com/en/glossary/total-float/)

## Distinction

Float results from the schedule calculation, whereas a time reserve is deliberately planned, for example as a separate buffer activity before an important milestone. In the critical chain method, safety margins are taken out of the individual activities and pooled in shared buffers. Float is room to manoeuvre that can be used up, whereas a lag is a mandatory waiting period.

## In practice

In the schedule for a school extension, the design of the outdoor areas has twenty days of float, the installation of the windows none. When the landscape architect is absent for two weeks, the project management remains calm because the float absorbs the delay. Shortly afterwards the windows are delayed by three days, and the handover moves back immediately. Since then, the team has looked first at the activities without float in every meeting.

## Frequently asked questions

### Who owns the float?

An often disputed question. If it is not explicitly settled, the float is usually used up by the first party to fall behind, and later activities no longer have it.

### What does negative float mean?

That an activity is calculated to finish later than the end date allows. Without countermeasures, the project will be completed late.

## Related terms

- [Total float](https://pmdecoder.com/en/glossary/total-float/)
- [Free float](https://pmdecoder.com/en/glossary/free-float/)
- [Critical path](https://pmdecoder.com/en/glossary/critical-path/)
- [Critical chain method](https://pmdecoder.com/en/glossary/critical-chain-method/)

---