# Fixed-price contract

- Framework: [cross-framework](https://pmdecoder.com/en/framework/general/)
- Concept: [Contract with a pre-agreed price](https://pmdecoder.com/en/concept/contract-with-a-pre-agreed-price/)
- Topic area: [Contracts and procurement](https://pmdecoder.com/en/area/contracts-and-procurement/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/fixed-price-contract/

## Definition

In a fixed-price contract, the parties agree a fixed price for a precisely described scope of work. The cost risk lies largely with the contractor: if it needs more effort than calculated, it bears the additional costs; if it works more efficiently, it keeps the profit. A precise statement of work is a prerequisite, because any later change in scope leads to change orders. Variants provide for price adjustment clauses or incentives for earlier completion.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Fixed-price contract](https://pmdecoder.com/en/glossary/fixed-price-contract-pmi/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Other terms

- Lump-sum contract (related, not equivalent)
- Firm fixed-price contract (related, not equivalent)

## Classification

- Broader term: [Contract](https://pmdecoder.com/en/glossary/contract/)

## Distinction

Under a cost-reimbursable contract, the contractor receives its actual costs plus a mark-up, and the cost risk lies with the client. Under a time and materials contract, the actual effort is billed at fixed rates. The lump-sum contract in construction (Pauschalvertrag) is a form of fixed-price contract in which deviations in quantities are also covered within certain limits.

## In practice

A municipality awards the implementation of a new council information system at a fixed price. The statement of work lists functions, interfaces, data migration and training in detail. When, after the start, the municipality asks for a connection to the citizen portal, the contractor submits a change order quotation, because this work had not been described. The municipality accepts, but would have obtained the connection more cheaply if it had been included in the original tender.

## Frequently asked questions

### Which undertakings is a fixed price suitable for?

For work whose scope can be described well and is unlikely to change much during delivery.

### Why are fixed prices often higher than effort estimates?

Because the contractor bears the cost risk and includes a risk premium in its calculation.

## Related terms

- [Cost-reimbursable contract](https://pmdecoder.com/en/glossary/cost-reimbursable-contract/)
- [Time and materials contract](https://pmdecoder.com/en/glossary/time-and-materials-contract/)
- [Statement of work](https://pmdecoder.com/en/glossary/statement-of-work/)
- [Contract claim](https://pmdecoder.com/en/glossary/contract-claim/)

---