# Fixed-price contract

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Contract with a pre-agreed price](https://pmdecoder.com/en/concept/contract-with-a-pre-agreed-price/)
- Topic area: [Contracts and procurement](https://pmdecoder.com/en/area/contracts-and-procurement/)
- Canonical version: https://pmdecoder.com/en/glossary/fixed-price-contract-pmi/

## Definition

Under a fixed-price contract, buyer and seller agree on a fixed price for a defined scope. The seller must deliver even if its costs turn out higher than calculated; the cost risk lies with the seller. PMI names common forms: firm fixed price without adjustment, fixed price incentive fee with an incentive for cost, schedule or performance targets, and fixed price with economic price adjustment, which allows price changes over long terms, for example based on an index. A clearly described scope is a prerequisite.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| cross-framework | [Fixed-price contract](https://pmdecoder.com/en/glossary/fixed-price-contract/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

In the glossary, “Festpreisvertrag” (fixed-price contract) represents the concept across frameworks; the PMI term is equivalent. Under a cost-reimbursable contract the buyer mainly bears the cost risk; under a time and materials contract billing is based on effort. Changes in scope almost always lead to renegotiation under a fixed-price contract.

## In practice

A municipality awards the renewal of the heating system in a sports hall. The bill of quantities and drawings are complete. The installation firm offers a fixed price and wins the contract. When it has to replace additional pipework during the work that was not in the bill of quantities, it submits a claim, which is negotiated separately.

## Frequently asked questions

### When is a fixed-price contract suitable?

When the scope is stable and precisely described and the seller can calculate costs reliably. With unclear requirements, sellers include high risk premiums or disputes arise.

### Is a fixed price always cheaper for the buyer?

Not necessarily. The seller prices in its risk, and changes become expensive through claims. The main benefit is the predictability of expenditure.

## Related terms

- [Fixed-price contract](https://pmdecoder.com/en/glossary/fixed-price-contract/)
- [Cost-reimbursable contract](https://pmdecoder.com/en/glossary/cost-reimbursable-contract-pmi/)
- [Time and materials contract](https://pmdecoder.com/en/glossary/time-and-materials-contract-pmi/)
- [Statement of work](https://pmdecoder.com/en/glossary/statement-of-work-pmi/)
- [Tendering](https://pmdecoder.com/en/glossary/tendering/)

---