# Finish-to-start relationship

abbr. FS

- Framework: [cross-framework](https://pmdecoder.com/en/framework/general/)
- Concept: [Start after the predecessor finishes](https://pmdecoder.com/en/concept/start-after-the-predecessor-finishes/)
- Topic area: [Network planning](https://pmdecoder.com/en/area/network-planning/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/finish-to-start-relationship/

## Definition

A finish-to-start relationship links the finish of a predecessor to the start of a successor. It is the most natural form of dependency: only when one piece of work is complete can the next build on it. A time interval can express that there is a waiting period in between, for example for curing, or that the two may overlap by a certain amount of time.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Finish-to-start](https://pmdecoder.com/en/glossary/finish-to-start/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Classification

- Broader term: [Logical relationship](https://pmdecoder.com/en/glossary/logical-relationship/)

## Distinction

The finish-to-start relationship is one of four logical relationships. Start-to-start links two starts, finish-to-finish two finishes, and start-to-finish ties the start of the predecessor to the finish of the successor. In scheduling tools, finish-to-start is usually the default.

## In practice

In a software project, acceptance testing can only begin once installation on the test system is complete. The planner links the two activities with a finish-to-start relationship. Because the test team needs another day after installation to load test data, she also enters a time interval of one day. If the installation is delayed, the software automatically moves the start of testing.

## Frequently asked questions

### How is the finish-to-start relationship abbreviated?

In English-language scheduling software as FS. In German, it is abbreviated as NF (Normalfolge) in network planning and often as EA (Ende-Anfang) in scheduling software.

### Can a finish-to-start relationship allow an overlap?

Yes, through a negative time interval. The successor may then start before the predecessor is fully complete.

## Related terms

- [Start-to-start relationship](https://pmdecoder.com/en/glossary/start-to-start-relationship/)
- [Finish-to-finish relationship](https://pmdecoder.com/en/glossary/finish-to-finish-relationship/)
- [Predecessor activity](https://pmdecoder.com/en/glossary/predecessor-activity/)
- [Successor activity](https://pmdecoder.com/en/glossary/successor-activity/)

---