# Finish-to-finish

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Finish after another activity finishes](https://pmdecoder.com/en/concept/finish-after-another-activity-finishes/)
- Topic area: [Network planning](https://pmdecoder.com/en/area/network-planning/)
- Canonical version: https://pmdecoder.com/en/glossary/finish-to-finish/

## Definition

Finish-to-finish, FF for short, is one of the four logical relationships PMI recognizes for linking activities in a schedule. It specifies that the successor cannot be completed before the predecessor is completed. The relationship does not govern when the two activities start; they can run largely in parallel. It is typical of activities that accompany or build on another, such as review, documentation or acceptance. A lag can express that the successor can only finish a certain time after the predecessor.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| cross-framework | [Finish-to-finish relationship](https://pmdecoder.com/en/glossary/finish-to-finish-relationship/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Classification

- Broader term: [Logical relationship](https://pmdecoder.com/en/glossary/logical-relationship-pmi/)

## Distinction

Finish-to-finish corresponds to the German Endfolge in network planning. Unlike finish-to-start, the successor may start before the predecessor ends; only the finish dates are linked. In start-to-start, by contrast, the starts are linked. The relationship is less common than finish-to-start and should be chosen deliberately.

## In practice

When a manual is written for a new machine, the technical writers work in parallel with the design team. The manual cannot be completed until the design is finished, however, because details keep changing until the end. The schedule therefore contains a finish-to-finish relationship with a lag of five days: the manual finishes no earlier than five days after the design.

## Frequently asked questions

### When is finish-to-finish more appropriate than finish-to-start?

When the successor can start early but its completion depends on the predecessor's result. With finish-to-start, the team would wait unnecessarily and the plan would become longer.

### Can an activity have several relationship types at once?

Yes. Finish-to-finish is often combined with start-to-start to tie a parallel activity to another at both start and finish. Not every scheduling tool supports two relationships between the same activities, however.

## Related terms

- [Finish-to-finish relationship](https://pmdecoder.com/en/glossary/finish-to-finish-relationship/)
- [Logical relationship](https://pmdecoder.com/en/glossary/logical-relationship-pmi/)
- [Finish-to-start](https://pmdecoder.com/en/glossary/finish-to-start/)
- [Start-to-start](https://pmdecoder.com/en/glossary/start-to-start/)
- [Start-to-finish](https://pmdecoder.com/en/glossary/start-to-finish/)

---