# Fast tracking

- Framework: [cross-framework](https://pmdecoder.com/en/framework/general/)
- Concept: [Shortening through parallel work](https://pmdecoder.com/en/concept/shortening-through-parallel-work/)
- Topic area: [Scheduling](https://pmdecoder.com/en/area/scheduling/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/fast-tracking/

## Definition

In fast tracking, activities that would normally wait for one another are started at the same time or carried out with an overlap. A typical example is starting implementation before design is fully complete, or starting tests while development is still under way. The technique only works for discretionary dependencies; mandatory dependencies cannot be removed.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Fast tracking](https://pmdecoder.com/en/glossary/fast-tracking-pmi/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Classification

- Broader term: [Schedule compression](https://pmdecoder.com/en/glossary/schedule-compression/)

## Distinction

Like crashing, fast tracking is a schedule compression technique. Initially it costs no extra money, but it increases the risk of rework, because later work builds on provisional results. Simultaneous engineering in product development is based on the same principle, but is designed as a permanent way of working rather than a short-term measure.

## In practice

So that an online shop can go live in time for the Christmas season, the agency starts technical implementation when only two thirds of the design have been approved. The basic page structure is built in parallel with the last design rounds. Two page types have to be adjusted again after final approval, which costs four days of rework. Overall, the project gains three weeks and keeps its launch date.

## Frequently asked questions

### Which activities are suitable for fast tracking?

Those with discretionary dependencies and stable interim results, where later changes cause little rework.

### How can the risk be limited?

By agreeing on stable interfaces early, keeping communication paths between the parallel teams short and allowing a time reserve for the rework that is to be expected.

## Related terms

- [Crashing](https://pmdecoder.com/en/glossary/crashing/)
- [Dependency](https://pmdecoder.com/en/glossary/dependency/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.