# Expert judgement

also: Expert estimate

- Framework: [cross-framework](https://pmdecoder.com/en/framework/general/)
- Concept: [Judgement by experts](https://pmdecoder.com/en/concept/judgement-by-experts/)
- Topic area: [Resources and estimating](https://pmdecoder.com/en/area/resources-and-estimating/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/expert-judgement/

## Definition

Expert judgement draws on the knowledge of people who are familiar with a subject, a technology, an industry or a type of undertaking. It is used where data are missing or insufficient, for example in estimates, the assessment of risks, the selection of solutions or the evaluation of bids. The experts may come from within the organization, from partners, from associations or from external consultancies.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Expert judgment](https://pmdecoder.com/en/glossary/expert-judgment/) | equivalent | — |

## Distinction

Expert judgement is a source of information, not a calculation method; structured techniques such as the Delphi method make it more robust. Historical data are based on measured values, expert judgement on experience and assessment. An expert opinion (Gutachten) is a formal, usually written and reasoned form of expert judgement.

## In practice

For the refurbishment of a listed town hall, there are no comparable projects in-house. The city therefore brings together a conservator, an experienced site manager from another heritage project and a structural engineer. Independently of one another, they estimate the duration of the facade refurbishment and then discuss the differences. The joint estimate, with a range, is fed into the schedule, and the assumptions are documented.

## Frequently asked questions

### How can expert judgements be made more robust?

Through several independent experts, documented assumptions, ranges instead of single values and structured techniques that limit mutual influence.

### What are the weaknesses of expert judgement?

It can be distorted by experience that does not transfer, by optimism or by the interests of those consulted. Disclosed assumptions help to detect this.

## Related terms

- [Delphi technique](https://pmdecoder.com/en/glossary/delphi-technique/)
- [Effort estimation](https://pmdecoder.com/en/glossary/effort-estimation/)
- [Historical data](https://pmdecoder.com/en/glossary/historical-data/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.