# Expected monetary value

abbr. EMV

- Framework: [cross-framework](https://pmdecoder.com/en/framework/general/)
- Concept: [Probability-weighted financial effect](https://pmdecoder.com/en/concept/probability-weighted-financial-effect/)
- Topic area: [Risks and opportunities](https://pmdecoder.com/en/area/risks-and-opportunities/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/expected-monetary-value/

## Definition

The expected monetary value is the probability of an event multiplied by its financial effect. Threats are entered with a negative sign, opportunities with a positive one. A risk with a probability of twenty per cent and damage of 50,000 euros has an expected monetary value of minus 10,000 euros. Added up across several risks, the figure provides a guide to the size of a risk reserve.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Expected monetary value](https://pmdecoder.com/en/glossary/expected-monetary-value-pmi/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

The expected monetary value is an average over many imagined repetitions: in any single case, a risk either occurs in full or not at all. Decision tree analysis uses it to compare alternatives with several possible outcomes. A simulation also shows the spread of possible results, which the expected monetary value alone conceals.

## In practice

For a festival, an organizer assesses four uncertainties: a severe storm with a probability of 15 per cent and damage of 200,000 euros, cancellation of the headline act at five per cent and 120,000 euros, additional security costs at 40 per cent and 30,000 euros, and the opportunity of an additional sponsor at 25 per cent and 40,000 euros. Together, the expected monetary values come to minus 38,000 euros. The organizer plans a reserve of this amount and also takes out weather insurance, because a storm alone would cost far more.

## Frequently asked questions

### Why is expected monetary value not sufficient as the only basis?

Because it smooths out rare but very expensive events. A single large risk can endanger a project even if its expected value is small.

### What does the abbreviation EMV stand for?

For expected monetary value. In German technical contexts, EMV is also the usual abbreviation for electromagnetic compatibility (elektromagnetische Verträglichkeit).

## Related terms

- [Decision tree analysis](https://pmdecoder.com/en/glossary/decision-tree-analysis/)
- [Risk contingency reserve](https://pmdecoder.com/en/glossary/risk-contingency-reserve/)
- [Quantitative risk analysis](https://pmdecoder.com/en/glossary/quantitative-risk-analysis/)
- [Opportunity](https://pmdecoder.com/en/glossary/opportunity/)

---