# Expected monetary value

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Probability-weighted financial effect](https://pmdecoder.com/en/concept/probability-weighted-financial-effect/)
- Topic area: [Risks and opportunities](https://pmdecoder.com/en/area/risks-and-opportunities/)
- Canonical version: https://pmdecoder.com/en/glossary/expected-monetary-value-pmi/

## Definition

In PMI usage, expected monetary value is a statistical technique that calculates the average financial outcome of a situation whose future scenarios may or may not occur. For each scenario, the monetary value of the impact is multiplied by its probability; the sum is the expected value. Threats are usually entered with a negative sign and opportunities with a positive one. The value does not describe an outcome that will actually occur but the average that would result from many repetitions. In projects it serves mainly to make risks comparable, to justify the size of the contingency reserve and to evaluate alternatives in decision tree analysis.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| cross-framework | [Expected monetary value](https://pmdecoder.com/en/glossary/expected-monetary-value/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

Expected monetary value corresponds to the cross-framework term Erwarteter Geldwert. It is a measure for individual risks or decisions; quantitative risk analysis, by contrast, considers the combined effect of all risks and often uses simulations for this. Despite the similar name, the term has nothing to do with earned value.

## In practice

In a construction project there is a 20 percent probability that groundwater will require additional dewatering costing 150,000 euros. At the same time there is a 40 percent chance that a cheaper supplier of precast elements will save 50,000 euros. The expected monetary value is minus 30,000 euros for the threat and plus 20,000 euros for the opportunity. The team takes both values into account when sizing the contingency reserve.

## Frequently asked questions

### Why is expected monetary value misleading for a single risk?

Because a single risk either occurs in full or not at all. An expected value of 30,000 euros does not mean that 30,000 euros of damage will occur, but either none or 150,000 euros. It is therefore most meaningful across many risks.

### Can expected monetary value also be used for schedules?

Yes, the same principle can be applied to time, for example in expected days of delay. The name refers to monetary values, however, because risks are easiest to aggregate and compare with budgets in that form.

## Related terms

- [Expected monetary value](https://pmdecoder.com/en/glossary/expected-monetary-value/)
- [Decision tree analysis](https://pmdecoder.com/en/glossary/decision-tree-analysis-pmi/)
- [Contingency reserve](https://pmdecoder.com/en/glossary/contingency-reserve/)
- [Quantitative risk analysis](https://pmdecoder.com/en/glossary/quantitative-risk-analysis-pmi/)
- [Opportunity](https://pmdecoder.com/en/glossary/opportunity-pmi/)
- [Threat](https://pmdecoder.com/en/glossary/threat-pmi/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.