# Executive (PRINCE2)

- Framework: [PRINCE2](https://pmdecoder.com/en/framework/prince2/)
- Reference: PRINCE2 7, Praktik Organisation
- Edition: PRINCE2 7
- Concept: [Senior sponsoring role in a project](https://pmdecoder.com/en/concept/senior-sponsoring-role-in-a-project/)
- Topic area: [Project organization](https://pmdecoder.com/en/area/project-organization/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/executive-prince2/

## Definition

The Executive is the person in PRINCE2 who is ultimately accountable for the project. The role is held by a single individual so that accountability is unambiguous, and it is filled by the commissioning organization. The Executive chairs the Project Board, represents the business interest and owns the business case. The Executive ensures that the project remains justified throughout its life and that the interests of the business, users and suppliers are kept in balance. Together with the commissioning organization, the Executive also appoints the project manager and secures funding.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | [Sponsor](https://pmdecoder.com/en/glossary/sponsor/) | closely related | Single individual who chairs the Project Board and owns the business case. |
| PMI / PMBOK Guide | [Sponsor](https://pmdecoder.com/en/glossary/sponsor-pmi/) | closely related | Single individual who chairs the Project Board and owns the business case. |
| PM² | [Project Owner](https://pmdecoder.com/en/glossary/project-owner/) | closely related | in PM², also sets the business objectives and chairs the Project Steering Committee |
| Six Sigma | [Champion](https://pmdecoder.com/en/glossary/champion/) | closely related | Often responsible for several improvement projects in an area and tied to tollgates and belt roles. |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

The project sponsor in ISO 21506 and the sponsor in PMI publications perform a similar function. The Executive, however, is firmly embedded in the Project Board and has the final say there. The project owner in PM² is comparable. The role shares only the word with the general English term for senior managers.

## In practice

When a city administration introduces a new payment system, the treasurer takes on the role of Executive. After hearing the other board members, she decides whether to include an expensive additional direct-debit feature and rejects it because the benefit does not justify the extra cost.

## Frequently asked questions

### Can the Executive combine the role with another?

On small projects the Executive can also act as Senior User. The Executive should not take on the project manager role, as direction and control would then be in the same hands.

### Why can there be only one Executive?

So that it is clear who makes the final decision and who is answerable to the commissioning organization. Shared accountability easily leads to nobody feeling responsible.

## Related terms

- [Sponsor](https://pmdecoder.com/en/glossary/sponsor/)
- [Sponsor](https://pmdecoder.com/en/glossary/sponsor-pmi/)
- [Project Owner](https://pmdecoder.com/en/glossary/project-owner/)
- [Project Board](https://pmdecoder.com/en/glossary/project-board/)
- [Continued business justification](https://pmdecoder.com/en/glossary/continued-business-justification/)
- [Business Case](https://pmdecoder.com/en/glossary/business-case-prince2/)
- [Senior User](https://pmdecoder.com/en/glossary/senior-user/)
- [Directing a project](https://pmdecoder.com/en/glossary/directing-a-project/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.