# Exception (PRINCE2)

- Framework: [PRINCE2](https://pmdecoder.com/en/framework/prince2/)
- Reference: PRINCE2 7, Praktik Fortschritt
- Edition: PRINCE2 7
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/exception-prince2/

## Definition

An exception exists in PRINCE2 when it is foreseeable that a plan will exceed its tolerances. What counts is the forecast, not the moment the limit has actually been crossed: as soon as it becomes apparent that time, cost or another aspect will end up outside the agreed margin, the responsible level must inform the level above. The Team Manager reports to the Project Manager, the Project Manager to the Project Board, and the Project Board to the commissioning organization. The level above then decides whether an exception plan is to be prepared, the tolerance adjusted, the project changed or the project closed.

## Equivalents in other frameworks

No equivalents have been recorded for this term yet.

## Distinction

A deviation within tolerance is not an exception; the responsible level resolves it itself. An issue or problem can lead to an exception but is not the same thing. The term has nothing to do with exceptions in software development, that is, runtime errors of a program.

## In practice

When a vehicle fleet is converted to electric vehicles, the grid connection for the charging stations is delayed by two months, while the tolerance is three weeks. The Project Manager reports the exception immediately, sets out its cause and consequences and proposes renting mobile chargers in the meantime. The Project Board requests an exception plan.

## Frequently asked questions

### Must an exception be reported before the tolerance is actually exceeded?

Yes. The approach relies on the forecast. The level above should be able to decide while options are still open.

### What happens to the existing plan in an exception?

The Project Board can request an exception plan that replaces the affected plan for the rest of its period, or take other decisions, such as closing the project.

## Related terms

- [Tolerance (PRINCE2)](https://pmdecoder.com/en/glossary/tolerance-prince2/)
- [Manage by exception principle](https://pmdecoder.com/en/glossary/manage-by-exception-principle/)
- [Project Board](https://pmdecoder.com/en/glossary/project-board/)
- [Corrective action](https://pmdecoder.com/en/glossary/corrective-action/)
- [Issue](https://pmdecoder.com/en/glossary/issue/)
- [Exception Report](https://pmdecoder.com/en/glossary/exception-report/)
- [Exception Plan](https://pmdecoder.com/en/glossary/exception-plan/)
- [Directing a project](https://pmdecoder.com/en/glossary/directing-a-project/)

---