# Estimate at completion

abbr. EAC

- Framework: [ISO 21506](https://pmdecoder.com/en/framework/iso-21506/)
- Reference: ISO 21506:2024/Amd 1:2026, 3.25
- Edition: ISO 21506:2024
- Concept: [Expected total cost at completion](https://pmdecoder.com/en/concept/expected-total-cost-at-completion/)
- Topic area: [Monitoring and control](https://pmdecoder.com/en/area/monitoring-and-control/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/estimate-at-completion/

## Definition

The estimate at completion connects past and future: it adds the actual cost already incurred to the cost still expected for the remaining work. The remaining cost can be re-estimated by those responsible or extrapolated from performance figures, for example by dividing the remaining budget by the cost performance index. Which approach fits depends on whether the variances so far are considered one-off or lasting. It can be produced for a whole project or programme just as well as for a control account, a single work package or an activity.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Estimate at completion](https://pmdecoder.com/en/glossary/estimate-at-completion-pmi/) | equivalent | — |

## Distinction

Budget at completion describes what the work should cost according to plan, the estimate at completion what it is likely to cost. The difference is the variance at completion. The estimate to complete covers only the share for the work still outstanding.

## In practice

The refurbishment of an office building has a budget at completion of 2.4 million euros. Halfway through the work, 1.4 million euros have been spent and earned value is 1.2 million euros. If cost efficiency stayed the same, extrapolation would give 2.8 million euros. The site management, however, considers the extra costs of the structural work to be a one-off, re-estimates the remaining work at 1.15 million euros and reports an estimate at completion of 2.55 million euros, with reasons.

## Frequently asked questions

### How often is the estimate at completion updated?

In every reporting period, usually monthly. A thorough reassessment of the remaining work makes sense above all after significant changes or after risks have materialized.

### Which formula is the right one?

None applies universally. Extrapolating with the cost performance index assumes that past efficiency will continue; a fresh estimate of the remaining work takes more effort but reflects known changes.

## Related terms

- [Estimate to complete](https://pmdecoder.com/en/glossary/estimate-to-complete/)
- [Budget at completion](https://pmdecoder.com/en/glossary/budget-at-completion/)
- [Variance at completion](https://pmdecoder.com/en/glossary/variance-at-completion/)
- [Project forecast](https://pmdecoder.com/en/glossary/project-forecast/)
- [Cost performance index](https://pmdecoder.com/en/glossary/cost-performance-index/)

---