# Estimate at completion

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Expected total cost at completion](https://pmdecoder.com/en/concept/expected-total-cost-at-completion/)
- Topic area: [Monitoring and control](https://pmdecoder.com/en/area/monitoring-and-control/)
- Canonical version: https://pmdecoder.com/en/glossary/estimate-at-completion-pmi/

## Definition

At PMI, the estimate at completion, abbreviated EAC, is the total of all costs expected, as of the data date, to be incurred by the time the work is completed. It is made up of the actual cost so far and the estimate to complete for the remaining work. PMI describes several ways of calculating it: a new bottom-up estimate of the remaining work, the assumption that the remaining work will proceed as budgeted, extrapolation with the current CPI (EAC = BAC / CPI) or extrapolation with both CPI and SPI. Which approach fits depends on whether the efficiency to date is expected to continue.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | [Estimate at completion](https://pmdecoder.com/en/glossary/estimate-at-completion/) | equivalent | — |

## Distinction

The PMI term is equivalent to “Schätzung bei Fertigstellung” (estimate at completion) according to ISO 21506, the lead term of the concept in the glossary. The budget at completion is the approved plan, the EAC the current expectation. The estimate to complete covers only the remaining cost. The difference between BAC and EAC is the variance at completion.

## In practice

A project with a BAC of 1.2 million euros has a CPI of 0.92 after half of the work. Extrapolation gives an EAC of around 1.3 million euros. The team considers the causes, costly onboarding of external staff, to have been overcome and re-estimates the remaining work. This bottom-up estimate comes to 1.25 million euros, which is reported to the steering committee as the forecast.

## Frequently asked questions

### Which EAC formula is the right one?

None is right in general. Extrapolating with the CPI assumes unchanged efficiency; assuming budgeted remaining work assumes that past variances were one-offs. The choice should be justified and stated in the report.

### How often is the estimate at completion updated?

In every reporting period in which earned value data is collected. It is important to track its development over time, because a steadily rising EAC points to a systematic problem.

## Related terms

- [Estimate at completion](https://pmdecoder.com/en/glossary/estimate-at-completion/)
- [Budget at completion](https://pmdecoder.com/en/glossary/budget-at-completion-pmi/)
- [Estimate to complete](https://pmdecoder.com/en/glossary/estimate-to-complete-pmi/)
- [Variance at completion](https://pmdecoder.com/en/glossary/variance-at-completion-pmi/)
- [Cost performance index](https://pmdecoder.com/en/glossary/cost-performance-index-pmi/)
- [Forecast](https://pmdecoder.com/en/glossary/forecast/)

---