# Enterprise environmental factors

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Influences and conditions around a project](https://pmdecoder.com/en/concept/influences-and-conditions-around-a-project/)
- Topic area: [Fundamentals](https://pmdecoder.com/en/area/fundamentals/)
- Canonical version: https://pmdecoder.com/en/glossary/enterprise-environmental-factors/

## Definition

Enterprise environmental factors, abbreviated EEF, are the circumstances that the project team cannot directly control but that shape, constrain or direct the project. PMI distinguishes internal factors, such as organizational culture, organizational structure, existing infrastructure, IT systems, available skills and the geographic distribution of facilities, from external factors, such as market conditions, laws and regulations, industry standards, social and cultural influences, the economic situation or physical environmental conditions. The factors can help or hinder a project. In its process descriptions PMI treats them throughout as an input to many planning and controlling processes, because hardly any decision can be made sensibly without considering these conditions.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| cross-framework | [Project environment](https://pmdecoder.com/en/glossary/project-environment/) | partially overlapping | covers only conditions outside the project's control, not the parties involved |

## Distinction

PMI contrasts enterprise environmental factors with organizational process assets: the latter are the organization’s plans, processes, templates and knowledge bases, which the project can use and in part tailor. EEF, by contrast, must be accepted by the project as given. Across frameworks the term corresponds to the project environment, but it focuses on the conditions that cannot be influenced rather than on the stakeholders usually included in the project environment. Individual factors may be recorded formally as constraints.

## In practice

A utility company plans to replace its billing software. During planning, the project manager records as external factors an upcoming change to metering regulations and the tight market for specialist consultants, and as internal factors the rule that only approved cloud providers may be used and a works council that must agree to any change to working-time systems. This list feeds into the schedule, procurement and the risk register.

## Frequently asked questions

### Can a project change enterprise environmental factors?

As a rule it cannot, at least not within its lifetime. The project can adapt to them, derive risks from them and, in individual cases, request an exception through governance. Lasting changes, for example to organizational culture, are a matter for the organization.

### Why record the factors explicitly?

Unspoken conditions lead to plans that fail in practice. A written overview shows which assumptions the plan rests on and helps new team members to understand the environment quickly.

## Related terms

- [Project environment](https://pmdecoder.com/en/glossary/project-environment/)
- [Constraint](https://pmdecoder.com/en/glossary/constraint/)
- [Project culture](https://pmdecoder.com/en/glossary/project-culture/)
- [Constraint](https://pmdecoder.com/en/glossary/constraint-pmi/)
- [Assumption](https://pmdecoder.com/en/glossary/assumption/)
- [Governance](https://pmdecoder.com/en/glossary/governance-pmi/)

---