# End Stage Report

- Framework: [PRINCE2](https://pmdecoder.com/en/framework/prince2/)
- Reference: PRINCE2 7, Prozess Managing a stage boundary
- Edition: PRINCE2 7
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/end-stage-report/

## Definition

In PRINCE2 the End Stage Report is the report the Project Manager prepares for the Project Board at the close of a management stage. It is produced at the transition to the next stage and assesses how the ending stage performed against its plan: which products were completed and accepted, how time and cost developed, which issues and risks are open and whether the business case still holds. Together with the plan for the next stage and the updated business case, it forms the basis on which the Board decides whether the project continues, is adjusted or is closed prematurely. No End Stage Report is produced for the final stage; the End Project Report takes its place.

## Equivalents in other frameworks

No equivalents have been recorded for this term yet.

## Distinction

The Highlight Report reports at fixed intervals during the stage; the End Stage Report looks back once on the whole stage and supports a decision. It therefore corresponds to the documents presented at a gate in ISO 21506, a phase gate at PMI or a phase transition in PM². Unlike the End Project Report, it covers only one stage and explicitly looks ahead to the next.

## In practice

After the concept stage of a project for a new warehouse management system, the project manager presents the End Stage Report to the Project Board. It shows that the functional design and supplier selection are complete, the stage ran four per cent over budget and, according to the bids, the expected savings will be somewhat lower. Together with the plan for the implementation stage he requests authorization for it; the Board grants it after reviewing the updated business case.

## Frequently asked questions

### When is the End Stage Report produced?

Towards the end of every management stage except the last, at the transition to the next stage. It is put before the Project Board before it decides whether to authorize the following stage.

### What happens if the End Stage Report shows a weak result?

The Project Board can still authorize the next stage, attach conditions, ask for the plans to be revised or close the project prematurely if the business case no longer holds.

## Related terms

- [Highlight Report](https://pmdecoder.com/en/glossary/highlight-report/)
- [End Project Report](https://pmdecoder.com/en/glossary/end-project-report/)
- [Gate](https://pmdecoder.com/en/glossary/gate/)
- [Phase Gate](https://pmdecoder.com/en/glossary/phase-gate/)
- [Phase gate](https://pmdecoder.com/en/glossary/phase-gate-pmi/)
- [Business case](https://pmdecoder.com/en/glossary/business-case/)
- [Managing a stage boundary](https://pmdecoder.com/en/glossary/managing-a-stage-boundary/)
- [Stage Plan](https://pmdecoder.com/en/glossary/stage-plan/)

---