# End Project Report

- Framework: [PRINCE2](https://pmdecoder.com/en/framework/prince2/)
- Reference: PRINCE2 7, Prozess Closing a project
- Edition: PRINCE2 7
- Concept: [Captured lessons from projects](https://pmdecoder.com/en/concept/captured-lessons-from-projects/)
- Topic area: [Closing](https://pmdecoder.com/en/area/closing/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/end-project-report/

## Definition

In PRINCE2 the End Project Report is the final report the Project Manager prepares for the Project Board when the project is closed. It compares what the project achieved with what was agreed at initiation: objectives, scope, cost, timescales, quality and tolerances. It describes which products were handed over and accepted, which issues and risks pass to operations or the user side, and which follow-on actions are recommended. It also assesses how the business case has developed and which benefits have already been realized or are still expected after the project ends. The Board bases its decision to close the project on this report. Lessons for future undertakings can be summarized in it or attached as a separate Lessons Report.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | [Lessons learned](https://pmdecoder.com/en/glossary/lessons-learned-iso/) | partially overlapping | Mainly evaluates project performance; lessons can be summarized in it or attached as a Lessons Report. |
| PMI / PMBOK Guide | [Lessons learned](https://pmdecoder.com/en/glossary/lessons-learned/) | partially overlapping | Mainly evaluates project performance; lessons can be summarized in it or attached as a Lessons Report. |
| PM² | [Project-End Report](https://pmdecoder.com/en/glossary/project-end-report/) | partially overlapping | contains lessons learned, but also reports on the performance and outcome of the project |
| Scrum | [Sprint Retrospective](https://pmdecoder.com/en/glossary/sprint-retrospective/) | partially overlapping | continually improves the way the team works instead of documenting lessons for other initiatives |

## Distinction

The End Stage Report covers a single stage and prepares the next; the End Project Report assesses the whole project and prepares its closure. The Lessons Report focuses on experience for others, the End Project Report on the performance of this project. The PM² Project-End Report combines both. The later review of whether benefits are actually realized usually lies outside the project in PRINCE2.

## In practice

After introducing a new payroll system, the project manager presents the End Project Report to the Project Board. All products have been accepted, the budget was underspent by two per cent, and the deadline was missed by one month. She hands over two open issues on travel expense claims to the operations team. The expected time savings in payroll accounting can only be measured after a year; the report states when and by whom this will be checked.

## Frequently asked questions

### Who receives the End Project Report?

The Project Board, which confirms project closure on its basis. Depending on the organization it also goes to a higher level, such as a programme or executive management.

### Does the End Project Report contain the lessons learned?

It can contain a summary. Detailed experience for future undertakings is often prepared in a separate Lessons Report, to which the End Project Report refers.

## Related terms

- [End Stage Report](https://pmdecoder.com/en/glossary/end-stage-report/)
- [Lessons Report](https://pmdecoder.com/en/glossary/lessons-report/)
- [Project-End Report](https://pmdecoder.com/en/glossary/project-end-report/)
- [Project closure](https://pmdecoder.com/en/glossary/project-closure/)
- [Business case](https://pmdecoder.com/en/glossary/business-case/)
- [Benefit](https://pmdecoder.com/en/glossary/benefit/)
- [Closing a project](https://pmdecoder.com/en/glossary/closing-a-project/)
- [Benefits Management Approach](https://pmdecoder.com/en/glossary/benefits-management-approach/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.