# Earned value measurements

also: Earned value metrics, EVM metrics

- Framework: [ISO 21506](https://pmdecoder.com/en/framework/iso-21506/)
- Reference: ISO 21506:2024, 3.24
- Edition: ISO 21506:2024
- Topic area: [Monitoring and control](https://pmdecoder.com/en/area/monitoring-and-control/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/earned-value-measurements/

## Definition

Earned value measurements are the figures from which earned value can be established and which make it usable for control. The basis is formed by planned value, earned value and actual cost. From these, variances such as cost and schedule variance, indices such as the cost and schedule performance indices, and forecasts such as the estimate at completion are derived. For programmes, the figures of the individual projects are combined, provided they were produced using the same rules.

## Equivalents in other frameworks

No equivalents have been recorded for this term yet.

## Distinction

The measurements are the values; earned value management is the method for collecting and interpreting them. Other project indicators, for example on quality or stakeholder satisfaction, are not part of them, even if they appear in the same report.

## In practice

The monthly report of an infrastructure programme shows the same six values for each of its five projects: planned value, earned value, actual cost, cost performance index, schedule performance index and estimate at completion. Because all projects measure using the same crediting rules, the programme office can combine the values into programme figures. A project that reports progress based on its own judgement is asked to switch to the agreed rules.

## Frequently asked questions

### Which measurements matter most?

For a quick overview, usually the cost and schedule performance indices, because they make projects of different sizes comparable. For budget decisions, the estimate at completion is what counts most.

### Why do the measurement rules have to be consistent?

Because figures produced under different rules cannot be meaningfully added up or compared. Otherwise a project with a generous estimate of its progress would look better than it is.

## Related terms

- [Earned value](https://pmdecoder.com/en/glossary/earned-value-iso/)
- [Earned value management](https://pmdecoder.com/en/glossary/earned-value-management/)
- [Schedule performance index](https://pmdecoder.com/en/glossary/schedule-performance-index/)
- [Cost performance index](https://pmdecoder.com/en/glossary/cost-performance-index/)
- [Cost variance](https://pmdecoder.com/en/glossary/cost-variance/)

---