# Earned value management

abbr. EVM

- Framework: [ISO 21506](https://pmdecoder.com/en/framework/iso-21506/)
- Reference: ISO 21506:2024, 3.22
- Edition: ISO 21506:2024
- Concept: [Performance measurement using earned value](https://pmdecoder.com/en/concept/performance-measurement-using-earned-value/)
- Topic area: [Monitoring and control](https://pmdecoder.com/en/area/monitoring-and-control/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/earned-value-management/

## Definition

Earned value management links three figures at a cut-off date: the planned value of the work scheduled up to then, the actual cost of the work performed and the earned value, that is, the budgeted value of the work actually accomplished. Because all three are based on the same baseline of scope, schedule and budget, cost and schedule variances, performance indices for cost and schedule and forecasts of total cost can be derived from them. This shows whether a project or programme is too expensive or too slow in relation to what it has achieved.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Earned value management](https://pmdecoder.com/en/glossary/earned-value-management-pmi/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

A simple comparison of planned and actual costs does not reveal whether the planned work was delivered for the money spent; the method closes this gap. ISO 21506 calls it earned value management. In German the name Earned-Value-Analyse is more common, whereas earned value management often refers to the entire control system, which includes not only the analysis but also the performance measurement baseline, control accounts and reporting.

## In practice

A software project with a budget of 500,000 euros takes stock after four months. Work worth 200,000 euros was planned, work packages with a planned value of 160,000 euros have been completed, and 190,000 euros have been spent. The project is therefore behind plan and more expensive than intended: for every euro of planned work it has spent about 1.19 euros. If this continues, it will cost just under 594,000 euros in total. The project manager presents these figures to the steering committee together with corrective actions.

## Frequently asked questions

### What is needed for earned value management?

A baseline with costs per work package over time, actual costs recorded using the same structure, and an agreed method for measuring percent complete.

### Is the method suitable for small projects?

In simplified form, yes, for example monthly with fixed progress steps per work package. The full set of formulas and control accounts is mainly worthwhile for large undertakings.

## Related terms

- [Earned value](https://pmdecoder.com/en/glossary/earned-value-iso/)
- [Planned value](https://pmdecoder.com/en/glossary/planned-value/)
- [Actual cost](https://pmdecoder.com/en/glossary/actual-cost/)
- [Cost variance](https://pmdecoder.com/en/glossary/cost-variance/)
- [Earned value measurements](https://pmdecoder.com/en/glossary/earned-value-measurements/)
- [Performance measurement baseline](https://pmdecoder.com/en/glossary/performance-measurement-baseline/)
- [Schedule variance](https://pmdecoder.com/en/glossary/schedule-variance/)
- [Percent complete](https://pmdecoder.com/en/glossary/percent-complete/)
- [Earned value](https://pmdecoder.com/en/glossary/earned-value/)

---