# Earned value management

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Performance measurement using earned value](https://pmdecoder.com/en/concept/performance-measurement-using-earned-value/)
- Topic area: [Monitoring and control](https://pmdecoder.com/en/area/monitoring-and-control/)
- Canonical version: https://pmdecoder.com/en/glossary/earned-value-management-pmi/

## Definition

At PMI, earned value management, abbreviated EVM, is a method that combines measurements of scope, schedule and resources to assess the performance and progress of a project. It is based on three values: planned value, earned value and actual cost. From these, variances such as cost variance and schedule variance, indices such as CPI and SPI, and forecasts such as the estimate at completion are derived. A prerequisite is an integrated performance measurement baseline managed through control accounts. PMI has published its own standard on EVM.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | [Earned value management](https://pmdecoder.com/en/glossary/earned-value-management/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

In the glossary, “Earned-Value-Analyse” (earned value analysis) according to ISO 21506 represents the concept; the PMI term is closely related. Besides the analysis, earned value management also covers the management system behind it: planning the baseline, responsibilities, data collection and control. Earned value is only one of the quantities EVM uses.

## In practice

A plant manufacturer introduces EVM for a major order. The work breakdown structure is divided into 25 control accounts, and each work package receives a budget, dates and a rule for measuring progress. The three basic values are collected monthly. As early as the third month, a falling CPI in engineering shows that rework is occurring, and the project manager takes countermeasures.

## Frequently asked questions

### Is earned value management suitable for small projects?

In simplified form, yes. Even a rough work breakdown structure with budgets and a simple rule for percentage of completion provides more meaningful information than merely comparing planned and actual costs.

### Can EVM be combined with adaptive approaches?

Yes. A common variant measures progress through completed story points or releases and derives earned value from them. The basic idea remains the same.

## Related terms

- [Earned value management](https://pmdecoder.com/en/glossary/earned-value-management/)
- [Earned value](https://pmdecoder.com/en/glossary/earned-value/)
- [Planned value](https://pmdecoder.com/en/glossary/planned-value-pmi/)
- [Actual cost](https://pmdecoder.com/en/glossary/actual-cost-pmi/)
- [Control account](https://pmdecoder.com/en/glossary/control-account-pmi/)
- [Performance measurement baseline](https://pmdecoder.com/en/glossary/performance-measurement-baseline-pmi/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.