# Earned value

also: Budgeted cost of work performed · abbr. EV, BCWP

- Framework: [ISO 21506](https://pmdecoder.com/en/framework/iso-21506/)
- Reference: ISO 21506:2024, 3.21
- Edition: ISO 21506:2024
- Concept: [Value of work performed](https://pmdecoder.com/en/concept/value-of-work-performed/)
- Topic area: [Monitoring and control](https://pmdecoder.com/en/area/monitoring-and-control/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/earned-value-iso/

## Definition

Earned value answers the question of how much of the planned work has already been done and expresses the answer in money. For each work package, the progress achieved is valued at its budget, and the results are added up across all packages. Because it uses the same unit as planned value and actual cost, it can be compared directly with both, which makes it the central figure of earned value management.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Earned value](https://pmdecoder.com/en/glossary/earned-value/) | equivalent | — |

## Distinction

Planned value shows which work should have been done by the cut-off date, earned value which work has been done, and actual cost what that work cost. It is closely linked to percent complete: the percentage expresses progress, earned value is the amount calculated from it. The PMBOK Guide uses the same figure under the same name.

## In practice

A software company has budgeted ten work packages totalling 400,000 euros for a customer portal. After three months, four packages worth 150,000 euros are complete, and a fifth worth 60,000 euros counts as half done under the agreed 50/50 rule. Earned value is therefore 180,000 euros. Planned value was 200,000 euros and actual cost 170,000 euros: the project is behind schedule but spending less than budgeted.

## Frequently asked questions

### How is progress measured for earned value?

Using rules agreed before work starts, such as 0/100 (credited only on completion), 50/50 (half credited at the start) or progress by completed interim milestones. Subjective percentage estimates are considered error-prone.

### Can earned value exceed the budget?

Not beyond the budget at completion. Once all the work is done, earned value equals exactly that budget, regardless of what the work actually cost.

## Related terms

- [Planned value](https://pmdecoder.com/en/glossary/planned-value/)
- [Actual cost](https://pmdecoder.com/en/glossary/actual-cost/)
- [Earned value management](https://pmdecoder.com/en/glossary/earned-value-management/)
- [Earned value measurements](https://pmdecoder.com/en/glossary/earned-value-measurements/)
- [Percent complete](https://pmdecoder.com/en/glossary/percent-complete/)
- [Earned value](https://pmdecoder.com/en/glossary/earned-value/)

---