# Early start date

also: Early start · abbr. ES

- Framework: [cross-framework](https://pmdecoder.com/en/framework/general/)
- Concept: [Earliest possible start of an activity](https://pmdecoder.com/en/concept/earliest-possible-start-of-an-activity/)
- Topic area: [Network planning](https://pmdecoder.com/en/area/network-planning/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/early-start-date/

## Definition

The early start date, ES for short, results from the forward pass. For the first activity, it is the project start. For every further activity, it corresponds to the latest of the dates that its predecessors impose on it through their links and time intervals. The activity cannot logically start before this point in time, even if staff and materials were available.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Early start date](https://pmdecoder.com/en/glossary/early-start-date-pmi/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

The early start plus the duration gives the early finish date. The late start date indicates how far the start can be postponed without consequences for the project end; the difference between the two values is the total float. The start actually scheduled may lie later than the early start, for example because resources only become available then.

## In practice

The installation of a facade has two predecessors: the building shell, which can be completed on 12 May, and the delivery of the facade elements, which has been promised for 19 May. The early start of the installation is therefore 19 May. When the facade contractor offers to start on the scaffolding as early as 15 May, the site management checks whether the scaffolding can be split off as a separate activity that depends only on the shell.

## Frequently asked questions

### How is the early start date calculated?

For finish-to-start relationships, as the largest early finish of all predecessors, each plus any time interval. Other types of relationship are taken into account accordingly.

### Does an activity have to start on its early start date?

No. It may start later, as long as it does not exceed its late start date.

## Related terms

- [Early finish date](https://pmdecoder.com/en/glossary/early-finish-date/)
- [Late start date](https://pmdecoder.com/en/glossary/late-start-date/)
- [Forward pass](https://pmdecoder.com/en/glossary/forward-pass/)
- [Total float](https://pmdecoder.com/en/glossary/total-float/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.