# Early start date

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Earliest possible start of an activity](https://pmdecoder.com/en/concept/earliest-possible-start-of-an-activity/)
- Topic area: [Network planning](https://pmdecoder.com/en/area/network-planning/)
- Canonical version: https://pmdecoder.com/en/glossary/early-start-date-pmi/

## Definition

The early start date, ES for short, is the earliest time an activity can start according to the logic of the network. It is determined in the forward pass of the critical path method: for the first activity it is the project start or the data date of the calculation, for all others it follows from the early finish dates of the predecessors, taking into account relationship type, lag and lead. If an activity has several predecessors, the latest of the resulting dates applies. Constraints such as “start no earlier than” can also push the early start date back.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| cross-framework | [Early start date](https://pmdecoder.com/en/glossary/early-start-date/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

The early start date corresponds to the German frühester Anfangszeitpunkt in network planning. The late start date, by contrast, indicates when an activity must start at the latest. The date on which the activity is actually scheduled may lie between the two, for example when resources only become available later. The real start is recorded as an actual date.

## In practice

For the introduction of a new point-of-sale system in a chain of stores, the scheduling tool calculates that the rollout in the first store can start on 12 March at the earliest, because only then will the hardware have been delivered and the test phase completed. Sales had hoped for early March; the early start date provides a factual explanation of why that is not possible without changes to the plan.

## Frequently asked questions

### Which value applies when there are several predecessors?

For finish-to-start relationships, the latest of the early finish dates of all predecessors, plus any lag. The activity can only start when all its prerequisites are met.

### Must an activity start on its early start date?

No. It can start later, up to its late start date, without jeopardizing the project end. Whether that is sensible depends on resources, risks and dependencies on its successors.

## Related terms

- [Early start date](https://pmdecoder.com/en/glossary/early-start-date/)
- [Early finish date](https://pmdecoder.com/en/glossary/early-finish-date-pmi/)
- [Late start date](https://pmdecoder.com/en/glossary/late-start-date-pmi/)
- [Forward pass](https://pmdecoder.com/en/glossary/forward-pass-pmi/)
- [Data date](https://pmdecoder.com/en/glossary/data-date/)

---