# Early finish date

also: Early finish · abbr. EF

- Framework: [cross-framework](https://pmdecoder.com/en/framework/general/)
- Concept: [Earliest possible finish of an activity](https://pmdecoder.com/en/concept/earliest-possible-finish-of-an-activity/)
- Topic area: [Network planning](https://pmdecoder.com/en/area/network-planning/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/early-finish-date/

## Definition

The early finish date, EF for short, is the sum of the early start date and the duration of the activity. It is determined in the forward pass and passed on to the successors, whose early start depends on it. The early finish of the last activity marks the earliest possible project end.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Early finish date](https://pmdecoder.com/en/glossary/early-finish-date-pmi/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

The late finish date states when an activity must be finished at the latest without endangering the project end. If the early finish and the late finish differ, the activity has float. The actual completion is only known as the project progresses and can lie before or after the early finish if the duration changes.

## In practice

A translation agency takes on a 400-page manual. The translation can start on 3 March, as soon as the source text has been released, and takes twenty working days; its early finish is therefore at the end of March. Because copy-editing follows immediately and the print date is fixed, the agency points out straight away that the release must not come a single day later. The early finish makes this chain comprehensible to the client.

## Frequently asked questions

### How is the early finish date calculated?

As early start plus duration. Depending on the counting convention, one day is subtracted so that a one-day activity starts and finishes on the same day.

### Why is the early finish of the last activity so important?

It shows the earliest possible project end. If it lies after the agreed date, action is needed.

## Related terms

- [Early start date](https://pmdecoder.com/en/glossary/early-start-date/)
- [Late finish date](https://pmdecoder.com/en/glossary/late-finish-date/)
- [Forward pass](https://pmdecoder.com/en/glossary/forward-pass/)
- [Free float](https://pmdecoder.com/en/glossary/free-float/)

---